Green Frog Power, Great Field Lane (20 MW battery storage)

Green Frog Power, Great Field Lane is a 20 MW battery storage project in Kingston upon Hull, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 2 May 2025, not yet built; the record was last updated on 12 May 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

20 MWbattery storage
approved, not builtstatus in REPD
12 May 2025record last updated
Kingston upon Hullcouncil area

Planning timeline

DateStage
23 December 2024Application submitted
2 May 2025Planning permission granted
2 May 2028Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
20 MW
Status (REPD)
approved, not built
Record last updated
12 May 2025
Operator or applicant
Pulse Clean Energy
Planning authority
Kingston upon Hull, City of
Planning application reference
24/01214/FULL
Address (REPD)
Standby Power Plant, Great Field Lane
Council area (by location)
Kingston upon Hull
Time to decision
19 weeks
Name in REPD
Green Frog Power, Great Field Lane - Battery Energy Storage System
REPD reference
18684

Who decides

ApplicationsKingston upon HullUK
Decided applications (solar, wind, battery)2910,236
Refused0 (0%)19%
Solar refused0 of 2512%
Onshore wind refused0 of 145%
Battery storage refused0 of 316%
Median time from submission to decision10.0 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Hull East Stor Generation Compoundbattery storage20approved, not built0.3
Salt End Lanebattery storage49permission expired1.3
Kingston International Business Parkbattery storage200approved, not built1.5
Neat Marsh North, Neat Marsh Road Solar Farmsolar farm49.9approved, not built1.8
Froghall Farm, Wyton Road Solar Farm & Battery Energy Storagebattery storage20approved, not built2.4
Froghall Farm, Wyton Road Solar Farm & Battery Energy Storagesolar farm49.9approved, not built2.4
Staithes Road, Saltend -Battery Energy Storage Systembattery storage240approved, not built2.8
Hull Solar Farmsolar farm25.7under construction3.0
Harbour Farm Solar Farmsolar farm42application submitted3.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.7472, -0.2516).