Froghall Farm, Wyton Road Solar Farm & Battery Energy Storage (49.9 MW)

Froghall Farm, Wyton Road Solar Farm & Battery Energy Storage is a 49.9 MW solar farm project in East Riding of Yorkshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 11 November 2024, not yet built; the record was last updated on 26 November 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
approved, not builtstatus in REPD
26 November 2024record last updated
East Riding of Yorkshirecouncil area

Planning timeline

DateStage
29 March 2023Application submitted
11 November 2024Planning permission granted
11 November 2029Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
26 November 2024
Operator or applicant
GAM Capital Limited
Planning authority
East Riding of Yorkshire
Planning application reference
23/00760/STPLFE
Site area
98.3 ha
Address (REPD)
South & W/O Froghall Farm, Wyton Road, Preston, Hull
Council area (by location)
East Riding of Yorkshire
Time to decision
85 weeks
Name in REPD
Froghall Farm, Wyton Road - Solar Farm & Battery Energy Storage
REPD reference
13654

The scheme also includes 20 MW of battery storage, recorded separately in REPD (approved, not built).

Who decides

ApplicationsEast Riding of YorkshireUK
Decided applications (solar, wind, battery)14310,236
Refused26 (18%)19%
Solar refused1 of 5912%
Onshore wind refused24 of 6345%
Battery storage refused1 of 2116%
Median time from submission to decision18.9 weeks17.0 weeks
Appeals lodged / allowed4 / 10—

Other large projects within 10 km

ProjectTypeMWStatuskm
Neat Marsh North, Neat Marsh Road Solar Farmsolar farm49.9approved, not built1.0
Hull Solar Farmsolar farm25.7under construction1.0
Staithes Road, Saltend -Battery Energy Storage Systembattery storage240approved, not built1.6
Kingston International Business Parkbattery storage200approved, not built2.0
Hull East Stor Generation Compoundbattery storage20approved, not built2.4
Green Frog Power, Great Field Lanebattery storage20approved, not built2.4
Salt End Lanebattery storage49permission expired3.0
Harbour Farm Solar Farmsolar farm42application submitted4.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.7657, -0.2315).