Solar, wind and battery projects near Hull (HU2)
66 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of HU2 (Kingston upon Hull): 4 are waiting for a planning decision, 44 approved but not yet running, 9 operational. The largest live scheme is Peartree Hill Solar Farm (320 MW solar farm, approved on 2 July 2026, not yet built), 9.9 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of HU2
Projects of 1 MW and more (32)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Energy Works Hullwind turbine | wind turbine | 3 | operationalupdated Mar 2018 | Jun 2011 | granted Oct 2011 | Mar 2018 | Kingston upon Hull | 1.1 |
| Clough Road Battery Energy Systembattery storage | battery storage | 130 | approved, not builtupdated Sep 2023 | Jun 2023 | granted Sep 2023 | Sep 2023 | Kingston upon Hull | 1.8 |
| Bericap, Oslo Roadrooftop solar | rooftop solar | 1.3 | approved, not built may be out of dateupdated Oct 2022 | Aug 2022 | granted Oct 2022 | Oct 2022 | Kingston upon Hull | 3.1 |
| Green Port Hull Wind Turbinewind turbine | wind turbine | 3 | application withdrawnupdated May 2012 | Dec 2011 | — | May 2012 | Kingston upon Hull | 3.5 |
| Croxby Hall Farm, Inglemire Lane Solar Farm & Battery Storagesolar farm | solar farm | 9.7 | application withdrawnupdated Mar 2024 | Aug 2023 | — | Mar 2024 | East Riding of Yorkshire | 4.2 |
| Snuff Mill Lane Gates Solar Farm & Battery Storagesolar farm | solar farm | 9.7 | application withdrawnupdated Mar 2024 | Aug 2023 | — | Mar 2024 | East Riding of Yorkshire | 4.8 |
| Hull East Stor Generation Compoundbattery storage | battery storage | 20 | approved, not built may be out of dateupdated May 2021 | Apr 2021 | granted Jul 2021 | May 2021 | Kingston upon Hull | 5.7 |
| Green Frog Power, Great Field Lanebattery storage | battery storage | 20 | approved, not builtupdated May 2025 | Dec 2024 | granted May 2025 | May 2025 | Kingston upon Hull | 5.9 |
| Bransholme, Hullbattery storage | battery storage | 18 | abandonedupdated Jan 2019 | Apr 2017 | — | Jan 2019 | Kingston upon Hull | 5.9 |
| Creyke Beck Substation Solar Farm & Battery Storagesolar farm | solar farm | 49.9 | approved, not built may be out of dateupdated Feb 2024 | Aug 2021 | granted Jan 2022 | Feb 2024 | East Riding of Yorkshire | 6.1 |
| Carlam Hill Education CICsolar farm | solar farm | 5 | operationalupdated Sep 2017 | Apr 2015 | granted Jun 2015 | Sep 2017 | Kingston upon Hull | 6.6 |
| Saltend Wind Turbinewind turbine | wind turbine | 1.3 | operationalupdated Jun 2010 | Dec 2005 | granted Mar 2006 | Jun 2010 | East Riding of Yorkshire | 6.9 |
| The Limes Wind Turbineswind farm | wind farm | 1.7 | operationalupdated Jul 2018 | May 2011 | granted Nov 2012 | Jul 2018 | East Riding of Yorkshire | 7.0 |
| Salt End Lanebattery storage | battery storage | 49 | permission expiredupdated Jul 2020 | Nov 2017 | granted Feb 2018 | Jul 2020 | East Riding of Yorkshire | 7.0 |
| Hull Solar Farmsolar farm | solar farm | 25.7 | under constructionupdated Jan 2020 | Jun 2015 | granted Oct 2015 | Jan 2020 | East Riding of Yorkshire | 7.1 |
| Kingston International Business Parkbattery storage | battery storage | 200 | approved, not builtupdated Nov 2025 | Oct 2024 | granted Jul 2025 | Nov 2025 | East Riding of Yorkshire | 7.3 |
| Neat Marsh North, Neat Marsh Road Solar Farmsolar farm | solar farm | 49.9 | approved, not builtupdated Jun 2026 | Jul 2025 | granted Feb 2026 | Jun 2026 | East Riding of Yorkshire | 7.4 |
| Froghall Farm, Wyton Road Solar Farm & Battery Energy Storagesolar farm | solar farm | 49.9 | approved, not builtupdated Nov 2024 | Mar 2023 | granted Nov 2024 | Nov 2024 | East Riding of Yorkshire | 7.4 |
| Froghall Farm, Wyton Road Solar Farm & Battery Energy Storagebattery storage | battery storage | 20 | approved, not builtupdated Nov 2024 | Mar 2023 | granted Nov 2024 | Nov 2024 | East Riding of Yorkshire | 7.4 |
| Pillswood Phase 1battery storage | battery storage | 49.5 | operationalupdated Nov 2022 | Apr 2017 | granted Oct 2018 | Nov 2022 | East Riding of Yorkshire | 7.5 |
| Creyke Beckbattery storage | battery storage | 49.9 | operationalupdated Jan 2019 | Apr 2017 | granted Jun 2017 | Jan 2019 | East Riding of Yorkshire | 7.5 |
| Cottingham Solar Farmsolar farm | solar farm | 5 | operationalupdated May 2022 | Jun 2021 | granted Mar 2022 | May 2022 | East Riding of Yorkshire | 7.5 |
| Pillswood Phase 2battery storage | battery storage | 49.5 | operationalupdated Nov 2022 | May 2019 | granted Jul 2023 | Nov 2022 | East Riding of Yorkshire | 7.6 |
| Kenley House Farm, Ferry Road Solar Farmsolar farm | solar farm | 49.9 | application submittedupdated Sep 2025 | Aug 2025 | — | Sep 2025 | East Riding of Yorkshire | 7.8 |
| Staithes Road, Saltend -Battery Energy Storage Systembattery storage | battery storage | 240 | approved, not builtupdated Nov 2025 | Dec 2024 | granted Jul 2025 | Nov 2025 | East Riding of Yorkshire | 8.5 |
| Humberfield Recycling Centrebattery storage | battery storage | 30 | approved, not builtupdated Nov 2025 | May 2025 | granted Jul 2025 | Nov 2025 | East Riding of Yorkshire | 8.5 |
| Carr House Farm, Drove Lanesolar farm | solar farm | 49.9 | approved, not builtupdated Sep 2023 | Jul 2023 | granted Sep 2023 | Sep 2023 | East Riding of Yorkshire | 8.8 |
| Kenley Solar Farmsolar farm | solar farm | 49.9 | approved, not built may be out of dateupdated Feb 2025 | May 2022 | granted Nov 2022 | Feb 2025 | East Riding of Yorkshire | 8.8 |
| Turf Carr Solar Farmsolar farm | solar farm | 49.9 | approved, not builtupdated Jun 2024 | Sep 2022 | granted May 2024 | Jun 2024 | East Riding of Yorkshire | 8.9 |
| Wren Kitchens & Bedrooms, Parrott Streetrooftop solar | rooftop solar | 6.6 | under construction | — | — | — | North Lincolnshire | 9.0 |
| Harbour Farm Solar Farmsolar farm | solar farm | 42 | application submittedupdated Oct 2025 | Sep 2025 | — | Oct 2025 | East Riding of Yorkshire | 9.3 |
| Peartree Hill Solar Farmsolar farm | solar farm | 320 | approved, not builtupdated Jul 2026 | Feb 2025 | granted Jul 2026 | Jul 2026 | East Riding of Yorkshire | 9.9 |
Smaller schemes under 1 MW, mostly rooftop solar (34)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Samaritans Spring Bank Solar Panelsrooftop solar | rooftop solar | — | operationalupdated Feb 2024 | Dec 2020 | granted Mar 2021 | Feb 2024 | Kingston upon Hull | 0.7 |
| Armadillo Storage, Spyvee Streetrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Nov 2025 | Aug 2025 | granted Oct 2025 | Nov 2025 | Kingston upon Hull | 0.9 |
| Caradon Ideal, National Avenuerooftop solar | rooftop solar | 0.6 | approved, not builtupdated Oct 2023 | Jul 2023 | granted Oct 2023 | Oct 2023 | Kingston upon Hull | 1.2 |
| Reckitt Benckiser Healthcare Limited, Dansom Lane Southrooftop solar | rooftop solar | 0.5 | approved, not builtupdated May 2025 | Jan 2025 | granted May 2025 | May 2025 | Kingston upon Hull | 1.3 |
| Hull Royal Infirmaryrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Feb 2026 | Nov 2025 | granted Jan 2026 | Feb 2026 | Kingston upon Hull | 1.4 |
| Smith And Nephew, Hessle Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Aug 2025 | May 2025 | granted Jul 2025 | Aug 2025 | Kingston upon Hull | 1.7 |
| Andrew Johnson Knudtzonrooftop solar | rooftop solar | 0.5 | approved, not builtupdated Dec 2021 | Oct 2021 | granted Dec 2021 | Dec 2021 | Kingston upon Hull | 2.3 |
| Andrew Johnson Knudtzon Limited, Boulevardrooftop solar | rooftop solar | 0.7 | approved, not builtupdated Feb 2024 | Dec 2023 | granted Feb 2024 | Feb 2024 | Kingston upon Hull | 2.4 |
| Staveley House, Stockholm Roadrooftop solar | rooftop solar | — | approved, not builtupdated Feb 2026 | Oct 2025 | granted Jan 2026 | Feb 2026 | Kingston upon Hull | 2.7 |
| Cranswick Foods, William Wright Dockrooftop solar | rooftop solar | 0.6 | approved, not builtupdated Jun 2026 | Dec 2025 | granted Feb 2026 | Jun 2026 | Kingston upon Hull | 2.8 |
| Cranswick Foods, Helsinki Roadrooftop solar | rooftop solar | 0.7 | approved, not built may be out of dateupdated Nov 2022 | Aug 2022 | granted Oct 2022 | Nov 2022 | Kingston upon Hull | 2.8 |
| Cranswick Foods, Helsinki Roadrooftop solar | rooftop solar | 0.5 | approved, not built may be out of dateupdated Nov 2022 | Aug 2022 | granted Oct 2022 | Nov 2022 | Kingston upon Hull | 2.8 |
| Cranswick Foods, Helsinki Road Solar Photovoltaicsrooftop solar | rooftop solar | 0.5 | approved, not builtupdated Nov 2022 | Aug 2022 | granted Nov 2022 | Nov 2022 | Kingston upon Hull | 2.8 |
| Cranswick Convenience Foods, Helsinki Roadrooftop solar | rooftop solar | 0.9 | approved, not built may be out of dateupdated Nov 2022 | Aug 2022 | granted Oct 2022 | Nov 2022 | Kingston upon Hull | 2.8 |
| Geneva Way Business Parkrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Jul 2022 | Jul 2022 | granted Sep 2022 | Jul 2022 | Kingston upon Hull | 2.9 |
| Cottingham Roadrooftop solar | rooftop solar | — | approved, not built may be out of dateupdated May 2022 | Apr 2022 | granted Jul 2022 | May 2022 | Kingston upon Hull | 2.9 |
| Victory Leisure Homesrooftop solar | rooftop solar | 0.8 | application submittedupdated Jan 2026 | Dec 2025 | — | Jan 2026 | Kingston upon Hull | 3.0 |
| Woodford Leisure Centre, Holderness Roadrooftop solar | rooftop solar | 0.5 | approved, not builtupdated Apr 2026 | Nov 2025 | granted Feb 2026 | Apr 2026 | Kingston upon Hull | 3.0 |
| XPO UK Supply Chain Limited, Salvesen Wayrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Jan 2025 | Oct 2024 | granted Dec 2024 | Jan 2025 | Kingston upon Hull | 3.3 |
| Morrisons Supermarket PV Solar Systemrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Mar 2022 | Feb 2022 | granted Apr 2022 | Mar 2022 | Kingston upon Hull | 3.5 |
| Croxby Hall Farm, Inglemire Lane Solar Farm & Battery Storagebattery storage | battery storage | — | application withdrawnupdated Mar 2024 | Aug 2023 | — | Mar 2024 | East Riding of Yorkshire | 4.2 |
| WJ Components Limited, Burma Driverooftop solar | rooftop solar | 0.1 | approved, not builtupdated Jul 2024 | Apr 2024 | granted Jul 2024 | Jul 2024 | Kingston upon Hull | 4.2 |
| Kingspan Access Floors,Burma Driverooftop solar | rooftop solar | 0.3 | approved, not built may be out of dateupdated Apr 2023 | Jan 2023 | granted Mar 2023 | Apr 2023 | Kingston upon Hull | 4.3 |
| Gibraltar Roadrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Jan 2024 | Nov 2023 | granted Jan 2024 | Jan 2024 | Kingston upon Hull | 4.7 |
| Gibraltar Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Feb 2022 | Jan 2022 | granted Apr 2022 | Feb 2022 | Kingston upon Hull | 4.7 |
| Snuff Mill Lane Gates Solar Farm & Battery Storagebattery storage | battery storage | — | application withdrawnupdated Mar 2024 | Aug 2023 | — | Mar 2024 | East Riding of Yorkshire | 4.8 |
| Great Field Lanebattery storage | battery storage | — | application withdrawnupdated Jan 2022 | Jan 2021 | — | Jan 2022 | Kingston upon Hull | 4.8 |
| Hull Portwind farm | wind farm | — | application submitted may be out of dateupdated Jul 2024 | Jun 2024 | — | Jul 2024 | Kingston upon Hull | 5.6 |
| Cottingham Water Pumping Station, Mill Housesolar farm | solar farm | 0.4 | approved, not builtupdated Oct 2023 | Jun 2023 | granted Sep 2023 | Oct 2023 | East Riding of Yorkshire | 5.8 |
| Creyke Beck Substationbattery storage | battery storage | — | approved, not builtupdated Feb 2024 | Dec 2023 | granted Mar 2024 | Feb 2024 | East Riding of Yorkshire | 6.1 |
| Spire Hospital, Lowfield Roadrooftop solar | rooftop solar | 0.3 | approved, not builtupdated May 2024 | Mar 2024 | granted Apr 2024 | May 2024 | East Riding of Yorkshire | 6.3 |
| Ferndale Park Newfields Industrial Estatebattery storage | battery storage | — | refusedupdated Nov 2018 | Oct 2017 | refused Jul 2018 | Nov 2018 | East Riding of Yorkshire | 6.6 |
| Luxinar Limited, Rofin Houserooftop solar | rooftop solar | 0.4 | approved, not builtupdated May 2023 | Feb 2023 | granted Apr 2023 | May 2023 | East Riding of Yorkshire | 8.4 |
| Peartree Hill Solar Farmbattery storage | battery storage | — | approved, not builtupdated Jul 2026 | Feb 2025 | granted Jul 2026 | Jul 2026 | East Riding of Yorkshire | 9.9 |
Distance from the average position of the HU2 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 15 | 2 | 9 | 2 | 0 | 737 |
| Rooftop solar | 28 | 1 | 26 | 1 | 0 | 18 |
| Wind farm | 2 | 1 | 0 | 1 | 0 | 0 |
| Wind turbine | 3 | 0 | 0 | 2 | 0 | 0 |
| Battery storage | 18 | 0 | 9 | 3 | 1 | 660 |
MW in pipeline: pending, approved and under-construction capacity.
How Kingston upon Hull decides solar, wind and battery applications
| Applications | Kingston upon Hull | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 29 | 10,236 |
| Refused | 0 (0%) | 19% |
| Solar refused | 0 of 25 | 12% |
| Onshore wind refused | 0 of 1 | 45% |
| Battery storage refused | 0 of 3 | 16% |
| Median time from submission to decision | 10.0 weeks | 17.0 weeks |
| Appeals lodged / allowed | 0 / 0 | — |
All projects in Kingston upon Hull
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near HU2, 10 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.