Energy Projects Near You

Carlam Hill Education CIC (5 MW solar farm)

Carlam Hill Education CIC is a 5 MW solar farm project in Kingston upon Hull, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 24 June 2016; the record was last updated on 29 September 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
29 September 2017record last updated
Kingston upon Hullcouncil area

Planning timeline

DateStage
23 April 2015Application submitted
12 June 2015Planning permission granted
18 January 2016Construction started
24 June 2016Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
29 September 2017
Operator or applicant
Greencoat (formerly Renesola)
Planning authority
Kingston upon Hull, City of
Planning application reference
15/00511/FULL
Site area
23.9 ha
Address (REPD)
Carlam Hill Farm, East of Cumbrian Way, Kingston Upon Hull
Council area (by location)
Kingston upon Hull
Time to decision
7 weeks
REPD reference
4804

Who decides

ApplicationsKingston upon HullUK
Decided applications (solar, wind, battery)2910,236
Refused0 (0%)19%
Solar refused0 of 2512%
Onshore wind refused0 of 145%
Battery storage refused0 of 316%
Median time from submission to decision10.0 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Bransholme, Hullbattery storage18abandoned1.0
Turf Carr Solar Farmsolar farm49.9approved, not built2.3
Kenley House Farm, Ferry Road Solar Farmsolar farm49.9application submitted2.9
Carr House Farm, Drove Lanesolar farm49.9approved, not built3.5
Kenley Solar Farmsolar farm49.9approved, not built3.5
Peartree Hill Solar Farmsolar farm320approved, not built3.6
Clough Road Battery Energy Systembattery storage130approved, not built4.9
Croxby Hall Farm, Inglemire Lane Solar Farm & Battery Storagesolar farm9.7application withdrawn6.1
Hull Solar Farmsolar farm25.7under construction6.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.8085, -0.3158).