Energy Projects Near You

Peartree Hill Solar Farm (320 MW)

Peartree Hill Solar Farm is a 320 MW solar farm project in East Riding of Yorkshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 2 July 2026, not yet built; the record was last updated on 13 July 2026. As a nationally significant project, it was decided by the Secretary of State for Energy Security and Net Zero on a Development Consent Order after examination by the Planning Inspectorate (EN010157).

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

320 MWsolar farm
approved, not builtstatus in REPD
13 July 2026record last updated
East Riding of Yorkshirecouncil area

Planning timeline

DateStage
21 February 2025Application submitted
2 July 2026Development consent granted (Secretary of State)
2 July 2031Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
320 MW
Status (REPD)
approved, not built
Record last updated
13 July 2026
Operator or applicant
JBM Solar / RWE
Planning authority
The Planning Inspectorate - National Infrastructure
Planning application reference
EN010157
Site area
891.0 ha
Address (REPD)
Meaux, Wawne, Beverley
Council area (by location)
East Riding of Yorkshire
Time to decision
71 weeks
REPD reference
15000

The scheme also includes battery storage, recorded separately in REPD (approved, not built).

Official project record at the Planning Inspectorate (EN010157)

Who decides

As a nationally significant project, it was decided by the Secretary of State for Energy Security and Net Zero on a Development Consent Order after examination by the Planning Inspectorate (EN010157). All Energy Secretary decisions on solar and wind farms. The Planning Inspectorate - National Infrastructure refused 7% of 46 decided solar, wind and battery applications in REPD (median 73 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Turf Carr Solar Farmsolar farm49.9approved, not built1.7
Kenley Solar Farmsolar farm49.9approved, not built1.9
Carr House Farm, Drove Lanesolar farm49.9approved, not built1.9
Kenley House Farm, Ferry Road Solar Farmsolar farm49.9application submitted2.6
Field House Solar Farmsolar farm40approved, not built3.4
Carlam Hill Education CICsolar farm5operational3.6
Carr Lane, Tickton Solar Farmsolar farm49.9approved, not built4.0
Hall Farm Routhwind farm24.6operational4.2
Bransholme, Hullbattery storage18abandoned4.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.8394, -0.3337).