Energy Projects Near You

Kenley Solar Farm (49.9 MW)

Kenley Solar Farm is a 49.9 MW solar farm project in East Riding of Yorkshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 18 November 2022, not yet built; the record was last updated on 25 February 2025. REPD also records that the planning permission expired on 18 November 2025, so the project may not go ahead in this form. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
approved, not builtmay be out of datestatus in REPD
25 February 2025record last updated
East Riding of Yorkshirecouncil area

REPD also records that the planning permission expired on 18 November 2025, so the project may not go ahead in this form.

Planning timeline

DateStage
18 May 2022Application submitted
18 November 2022Planning permission granted
18 November 2025Permission expired

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
25 February 2025
Operator or applicant
Boom Power Limited
Planning authority
East Riding of Yorkshire
Planning application reference
22/01208/STPLF
Site area
94.0 ha
Address (REPD)
North East And West Of Carr Plantation Ferry Road Wawne
Council area (by location)
East Riding of Yorkshire
Time to decision
26 weeks
REPD reference
11367

Who decides

ApplicationsEast Riding of YorkshireUK
Decided applications (solar, wind, battery)14310,236
Refused26 (18%)19%
Solar refused1 of 5912%
Onshore wind refused24 of 6345%
Battery storage refused1 of 2116%
Median time from submission to decision18.9 weeks17.0 weeks
Appeals lodged / allowed4 / 10—

Other large projects within 10 km

ProjectTypeMWStatuskm
Carr House Farm, Drove Lanesolar farm49.9approved, not built<0.1
Kenley House Farm, Ferry Road Solar Farmsolar farm49.9application submitted1.0
Peartree Hill Solar Farmsolar farm320approved, not built1.9
Turf Carr Solar Farmsolar farm49.9approved, not built2.7
Carlam Hill Education CICsolar farm5operational3.5
Carr Lane, Tickton Solar Farmsolar farm49.9approved, not built3.9
Field House Solar Farmsolar farm40approved, not built4.4
Bransholme, Hullbattery storage18abandoned4.5
Pillswood Phase 1battery storage49.5operational4.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.8292, -0.3567).