Turf Carr Solar Farm (49.9 MW)

Turf Carr Solar Farm is a 49.9 MW solar farm project in East Riding of Yorkshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 29 May 2024, not yet built; the record was last updated on 13 June 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
approved, not builtstatus in REPD
13 June 2024record last updated
East Riding of Yorkshirecouncil area

Planning timeline

DateStage
13 September 2022Application submitted
29 May 2024Planning permission granted
29 May 2029Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
13 June 2024
Operator or applicant
Anesco Limited
Planning authority
East Riding of Yorkshire
Planning application reference
22/02775/STPLF
Site area
64.3 ha
Address (REPD)
Wawne Common Lane Bridge Wawne Common Road Wawne
Council area (by location)
East Riding of Yorkshire
Time to decision
89 weeks
REPD reference
11214

Who decides

ApplicationsEast Riding of YorkshireUK
Decided applications (solar, wind, battery)14310,236
Refused26 (18%)19%
Solar refused1 of 5912%
Onshore wind refused24 of 6345%
Battery storage refused1 of 2116%
Median time from submission to decision18.9 weeks17.0 weeks
Appeals lodged / allowed4 / 10—

Other large projects within 10 km

ProjectTypeMWStatuskm
Peartree Hill Solar Farmsolar farm320approved, not built1.7
Carlam Hill Education CICsolar farm5operational2.3
Kenley Solar Farmsolar farm49.9approved, not built2.7
Carr House Farm, Drove Lanesolar farm49.9approved, not built2.7
Kenley House Farm, Ferry Road Solar Farmsolar farm49.9application submitted2.8
Bransholme, Hullbattery storage18abandoned3.2
Field House Solar Farmsolar farm40approved, not built4.9
Carr Lane, Tickton Solar Farmsolar farm49.9approved, not built5.7
Hall Farm Routhwind farm24.6operational5.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.8291, -0.3151).