Pillswood Phase 1 (49.5 MW battery storage)

Pillswood Phase 1 is a 49.5 MW battery storage project in East Riding of Yorkshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 November 2022; the record was last updated on 9 November 2022.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.5 MWbattery storage
operationalstatus in REPD
9 November 2022record last updated
East Riding of Yorkshirecouncil area

Planning timeline

DateStage
6 April 2017Application submitted
30 October 2018Planning permission granted
1 April 2022Construction started
1 November 2022Operational

Project details

Technology
battery storage (stand-alone storage)
Capacity
49.5 MW
Status (REPD)
operational
Record last updated
9 November 2022
Operator or applicant
Harmony Energy Storage
Planning authority
East Riding of Yorkshire
Planning application reference
17/01993/STPLF
Address (REPD)
Land South East Of Lawns Farm, Park Lane, Cottingham, East Riding Of Yorkshire
Council area (by location)
East Riding of Yorkshire
Time to decision
82 weeks
REPD reference
7005

Who decides

ApplicationsEast Riding of YorkshireUK
Decided applications (solar, wind, battery)14310,236
Refused26 (18%)19%
Solar refused1 of 5912%
Onshore wind refused24 of 6345%
Battery storage refused1 of 2116%
Median time from submission to decision18.9 weeks17.0 weeks
Appeals lodged / allowed4 / 10—

Other large projects within 10 km

ProjectTypeMWStatuskm
Pillswood Phase 2battery storage49.5operational0.2
Creyke Beckbattery storage49.9operational0.5
Creyke Beck Substation Solar Farm & Battery Storagesolar farm49.9approved, not built2.3
Snuff Mill Lane Gates Solar Farm & Battery Storagesolar farm9.7application withdrawn3.1
Croxby Hall Farm, Inglemire Lane Solar Farm & Battery Storagesolar farm9.7application withdrawn3.4
Cottingham Solar Farmsolar farm5operational4.1
Kenley House Farm, Ferry Road Solar Farmsolar farm49.9application submitted4.4
Carr House Farm, Drove Lanesolar farm49.9approved, not built4.9
Kenley Solar Farmsolar farm49.9approved, not built4.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.8013, -0.4151).