Cottingham Solar Farm (5 MW)

Cottingham Solar Farm is a 5 MW solar farm project in East Riding of Yorkshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 February 2022; the record was last updated on 12 May 2022.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
12 May 2022record last updated
East Riding of Yorkshirecouncil area

Planning timeline

DateStage
8 June 2021Application submitted
1 September 2021Construction started
1 February 2022Operational
14 March 2022Planning permission granted

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
12 May 2022
Operator or applicant
Hull & East Yorkshire Hospitals NHS Trust
Planning authority
East Riding of Yorkshire
Planning application reference
21/02126/STPLF
Site area
7.7 ha
Address (REPD)
S/O Castle Hill Roundabout To The E/O Beverley Road, Cottingham, Hull
Council area (by location)
East Riding of Yorkshire
Time to decision
40 weeks
Name in REPD
Cottingham - Solar Farm
REPD reference
9179

Who decides

ApplicationsEast Riding of YorkshireUK
Decided applications (solar, wind, battery)14310,236
Refused26 (18%)19%
Solar refused1 of 5912%
Onshore wind refused24 of 6345%
Battery storage refused1 of 2116%
Median time from submission to decision18.9 weeks17.0 weeks
Appeals lodged / allowed4 / 10—

Other large projects within 10 km

ProjectTypeMWStatuskm
Creyke Beck Substation Solar Farm & Battery Storagesolar farm49.9approved, not built2.3
Snuff Mill Lane Gates Solar Farm & Battery Storagesolar farm9.7application withdrawn3.1
Creyke Beckbattery storage49.9operational3.6
Croxby Hall Farm, Inglemire Lane Solar Farm & Battery Storagesolar farm9.7application withdrawn4.0
Pillswood Phase 1battery storage49.5operational4.1
Pillswood Phase 2battery storage49.5operational4.2
Humberfield Recycling Centrebattery storage30approved, not built5.3
Clough Road Battery Energy Systembattery storage130approved, not built7.2
Melton Waste Parkwind farm5operational8.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.7702, -0.4498).