Snuff Mill Lane Gates Solar Farm & Battery Storage (9.7 MW)

Snuff Mill Lane Gates Solar Farm & Battery Storage is a 9.7 MW solar farm project in East Riding of Yorkshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application withdrawn on 5 March 2024; the record was last updated on 20 March 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

9.7 MWsolar farm
application withdrawnstatus in REPD
20 March 2024record last updated
East Riding of Yorkshirecouncil area

Planning timeline

DateStage
25 August 2023Application submitted
5 March 2024Application withdrawn

Project details

Technology
solar farm
Capacity
9.7 MW
Status (REPD)
application withdrawn
Record last updated
20 March 2024
Operator or applicant
UOH Energy Co Limited
Planning authority
East Riding of Yorkshire
Planning application reference
23/02046/STPLF
Site area
5.9 ha
Address (REPD)
North Of Snuff Mill Lane Gates Snuff Mill Lane Cottingham
Council area (by location)
East Riding of Yorkshire
Name in REPD
Snuff Mill Lane Gates - Solar Farm & Battery Storage
REPD reference
14858

The scheme also includes battery storage, recorded separately in REPD (application withdrawn).

Who decides

ApplicationsEast Riding of YorkshireUK
Decided applications (solar, wind, battery)14310,236
Refused26 (18%)19%
Solar refused1 of 5912%
Onshore wind refused24 of 6345%
Battery storage refused1 of 2116%
Median time from submission to decision18.9 weeks17.0 weeks
Appeals lodged / allowed4 / 10—

Other large projects within 10 km

ProjectTypeMWStatuskm
Croxby Hall Farm, Inglemire Lane Solar Farm & Battery Storagesolar farm9.7application withdrawn0.9
Creyke Beck Substation Solar Farm & Battery Storagesolar farm49.9approved, not built1.3
Creyke Beckbattery storage49.9operational2.9
Pillswood Phase 1battery storage49.5operational3.1
Cottingham Solar Farmsolar farm5operational3.1
Pillswood Phase 2battery storage49.5operational3.3
Clough Road Battery Energy Systembattery storage130approved, not built4.2
Kenley House Farm, Ferry Road Solar Farmsolar farm49.9application submitted6.0
Carr House Farm, Drove Lanesolar farm49.9approved, not built6.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.7742, -0.4026).