Elstronwick, Burstwick - Daisy Hill Solar Photovoltaic Farm (35 MW)
Elstronwick, Burstwick - Daisy Hill Solar Photovoltaic Farm is a 35 MW solar farm project in East Riding of Yorkshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 30 January 2026, not yet built; the record was last updated on 31 March 2026.
35 MWsolar farm
approved, not builtstatus in REPD
31 March 2026record last updated
East Riding of Yorkshirecouncil area
Planning timeline
| Date | Stage |
|---|---|
| 27 June 2024 | Application submitted |
| 30 January 2026 | Planning permission granted |
| 30 January 2031 | Permission due to expire (unless work starts) |
Project details
- Technology
- solar farm
- Capacity
- 35 MW
- Status (REPD)
- approved, not built
- Record last updated
- 31 March 2026
- Operator or applicant
- Enviromena Project Management UK Limited
- Planning authority
- East Riding of Yorkshire
- Planning application reference
- 24/01484/STPLF
- Site area
- 50.4 ha
- Address (REPD)
- Elstronwick, Burstwick, Hull
- Council area (by location)
- East Riding of Yorkshire
- Time to decision
- 83 weeks
- REPD reference
- 16816
Who decides
| Applications | East Riding of Yorkshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 143 | 10,236 |
| Refused | 26 (18%) | 19% |
| Solar refused | 1 of 59 | 12% |
| Onshore wind refused | 24 of 63 | 45% |
| Battery storage refused | 1 of 21 | 16% |
| Median time from submission to decision | 18.9 weeks | 17.0 weeks |
| Appeals lodged / allowed | 4 / 10 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Burton Pidsea (Wadworth Hill) Wind Farm | wind farm | 10.2 | operational | 2.2 |
| Harbour Farm Solar Farm | solar farm | 42 | application submitted | 4.2 |
| Staithes Road, Saltend -Battery Energy Storage System | battery storage | 240 | approved, not built | 4.4 |
| Roos Wind Farm (Resubmission) | wind farm | 17.1 | operational | 5.0 |
| Kingston International Business Park | battery storage | 200 | approved, not built | 5.5 |
| Neat Marsh North, Neat Marsh Road Solar Farm | solar farm | 49.9 | approved, not built | 5.5 |
| Froghall Farm, Wyton Road Solar Farm & Battery Energy Storage | battery storage | 20 | approved, not built | 5.8 |
| Froghall Farm, Wyton Road Solar Farm & Battery Energy Storage | solar farm | 49.9 | approved, not built | 5.8 |
| Salt End Lane | battery storage | 49 | permission expired | 6.1 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.7518, -0.1461).