Energy Projects Near You

Roos Wind Farm (Resubmission) (17.1 MW)

Roos Wind Farm (Resubmission) is a 17.1 MW wind farm project in East Riding of Yorkshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 2 April 2013; the record was last updated on 4 June 2013.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

17.1 MWwind farm
operationalstatus in REPD
4 June 2013record last updated
East Riding of Yorkshirecouncil area

Planning timeline

DateStage
20 January 2009Application submitted
11 August 2009Refused by the planning authority
13 May 2010Planning permission granted
13 May 2010Appeal allowed
1 March 2012Construction started
2 April 2013Operational

Project details

Technology
wind farm
Capacity
17.1 MW
Status (REPD)
operational
Record last updated
4 June 2013
Operator or applicant
Renewable Energy Systems (RES)
Planning authority
East Riding of Yorkshire
Planning application reference
08/05692/STPLFE
Appeal reference
09/00134/REFUSE
Turbines
9
Address (REPD)
Land To The West Of Ivy House Rectory Road Roos East Riding Of Yorkshire
Council area (by location)
East Riding of Yorkshire
Time to decision
68 weeks
REPD reference
3835

Who decides

ApplicationsEast Riding of YorkshireUK
Decided applications (solar, wind, battery)14310,236
Refused26 (18%)19%
Solar refused1 of 5912%
Onshore wind refused24 of 6345%
Battery storage refused1 of 2116%
Median time from submission to decision18.9 weeks17.0 weeks
Appeals lodged / allowed4 / 10—

Other large projects within 10 km

ProjectTypeMWStatuskm
Monkwith Wind Farmwind farm6.9refused on appeal1.9
Tedder Hill Wind clusterwind farm7.5operational2.8
Burton Pidsea (Wadworth Hill) Wind Farmwind farm10.2operational2.9
Elstronwick, Burstwick - Daisy Hill Solar Photovoltaic Farmsolar farm35approved, not built5.0
Redhall Industrial Estatesolar farm5operational6.1
Far Marsh Farmwind farm7.5operational8.8
Harbour Farm Solar Farmsolar farm42application submitted8.9
Eastfield Farm Wind Farmwind farm11.4refused9.4
Staithes Road, Saltend -Battery Energy Storage Systembattery storage240approved, not built9.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.7518, -0.0697).