Roos Wind Farm (Resubmission) (17.1 MW)
Roos Wind Farm (Resubmission) is a 17.1 MW wind farm project in East Riding of Yorkshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 2 April 2013; the record was last updated on 4 June 2013.
17.1 MWwind farm
operationalstatus in REPD
4 June 2013record last updated
East Riding of Yorkshirecouncil area
Planning timeline
| Date | Stage |
|---|---|
| 20 January 2009 | Application submitted |
| 11 August 2009 | Refused by the planning authority |
| 13 May 2010 | Planning permission granted |
| 13 May 2010 | Appeal allowed |
| 1 March 2012 | Construction started |
| 2 April 2013 | Operational |
Project details
- Technology
- wind farm
- Capacity
- 17.1 MW
- Status (REPD)
- operational
- Record last updated
- 4 June 2013
- Operator or applicant
- Renewable Energy Systems (RES)
- Planning authority
- East Riding of Yorkshire
- Planning application reference
- 08/05692/STPLFE
- Appeal reference
- 09/00134/REFUSE
- Turbines
- 9
- Address (REPD)
- Land To The West Of Ivy House Rectory Road Roos East Riding Of Yorkshire
- Council area (by location)
- East Riding of Yorkshire
- Time to decision
- 68 weeks
- REPD reference
- 3835
Who decides
| Applications | East Riding of Yorkshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 143 | 10,236 |
| Refused | 26 (18%) | 19% |
| Solar refused | 1 of 59 | 12% |
| Onshore wind refused | 24 of 63 | 45% |
| Battery storage refused | 1 of 21 | 16% |
| Median time from submission to decision | 18.9 weeks | 17.0 weeks |
| Appeals lodged / allowed | 4 / 10 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Monkwith Wind Farm | wind farm | 6.9 | refused on appeal | 1.9 |
| Tedder Hill Wind cluster | wind farm | 7.5 | operational | 2.8 |
| Burton Pidsea (Wadworth Hill) Wind Farm | wind farm | 10.2 | operational | 2.9 |
| Elstronwick, Burstwick - Daisy Hill Solar Photovoltaic Farm | solar farm | 35 | approved, not built | 5.0 |
| Redhall Industrial Estate | solar farm | 5 | operational | 6.1 |
| Far Marsh Farm | wind farm | 7.5 | operational | 8.8 |
| Harbour Farm Solar Farm | solar farm | 42 | application submitted | 8.9 |
| Eastfield Farm Wind Farm | wind farm | 11.4 | refused | 9.4 |
| Staithes Road, Saltend -Battery Energy Storage System | battery storage | 240 | approved, not built | 9.4 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.7518, -0.0697).