Eastfield Farm Wind Farm (11.4 MW)
Eastfield Farm Wind Farm is an 11.4 MW wind farm project in East Riding of Yorkshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 11 September 2000; the record was last updated on 5 August 2005.
11.4 MWwind farm
refusedstatus in REPD
5 August 2005record last updated
East Riding of Yorkshirecouncil area
Planning timeline
| Date | Stage |
|---|---|
| 8 September 1998 | Application submitted |
| 11 September 2000 | Refused by the planning authority |
Project details
- Technology
- wind farm
- Capacity
- 11.4 MW
- Status (REPD)
- refused
- Record last updated
- 5 August 2005
- Operator or applicant
- Renewable Energy Systems (RES)
- Planning authority
- East Riding of Yorkshire
- Planning application reference
- 347/10029A
- Address (REPD)
- Hollym Holderness
- Council area (by location)
- East Riding of Yorkshire
- Time to decision
- 105 weeks
- REPD reference
- 2662
Who decides
| Applications | East Riding of Yorkshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 143 | 10,236 |
| Refused | 26 (18%) | 19% |
| Solar refused | 1 of 59 | 12% |
| Onshore wind refused | 24 of 63 | 45% |
| Battery storage refused | 1 of 21 | 16% |
| Median time from submission to decision | 18.9 weeks | 17.0 weeks |
| Appeals lodged / allowed | 4 / 10 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Out Newton Wind Farm | wind farm | 9 | operational | 5.1 |
| Skeffling Wind Farm | wind farm | 11.5 | application withdrawn | 5.5 |
| Redhall Industrial Estate | solar farm | 5 | operational | 6.5 |
| Tedder Hill Wind cluster | wind farm | 7.5 | operational | 7.6 |
| Monkwith Wind Farm | wind farm | 6.9 | refused on appeal | 9.1 |
| Roos Wind Farm (Resubmission) | wind farm | 17.1 | operational | 9.4 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.6951, 0.0356).