Energy Projects Near You

Solar, wind and battery projects near Withernsea (HU19)

12 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of HU19 (East Riding of Yorkshire): 4 approved but not yet running, 4 operational. The largest live scheme is Bowmar Carr Road, Burton Pidsea (1 MW solar farm, approved on 27 October 2022, not yet built; REPD status may be out of date), 9.4 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

12projects within 10 km
0awaiting a decision
4approved, not running
4operational

Projects within 10 km of HU19

Projects of 1 MW and more (9)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Eastfield Farm Wind Farmwind farmwind farm11.4refusedupdated Aug 2005Sep 1998refused Sep 2000Aug 2005East Riding of Yorkshire3.1
Tedder Hill Wind clusterwind farmwind farm7.5operationalupdated Mar 2014May 2006granted Jan 2010Mar 2014East Riding of Yorkshire5.1
Monkwith Wind Farmwind farmwind farm6.9refused on appealupdated Dec 2011Jun 2009refused Jan 2010Dec 2011East Riding of Yorkshire6.7
Redhall Industrial Estatesolar farmsolar farm5operationalupdated Feb 2015Oct 2012granted Jan 2013Feb 2015East Riding of Yorkshire7.1
Out Newton Wind Farmwind farmwind farm9operationalupdated Apr 2009Nov 1998granted Sep 2000Apr 2009East Riding of Yorkshire7.4
Roos Wind Farm (Resubmission)wind farmwind farm17.1operationalupdated Jun 2013Jan 2009granted May 2010Jun 2013East Riding of Yorkshire7.5
Skeffling Wind Farmwind farmwind farm11.5application withdrawnupdated May 2015Jan 2012—May 2015East Riding of Yorkshire8.1
Outstray Farm Wind Projectwind farmwind farm1.8application withdrawnupdated Aug 2005Jun 1999—Aug 2005East Riding of Yorkshire8.5
Bowmar Carr Road, Burton Pidseasolar farmsolar farm1approved, not built may be out of dateupdated Jun 2022Jun 2022granted Oct 2022Jun 2022East Riding of Yorkshire9.4
Smaller schemes under 1 MW, mostly rooftop solar (3)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Withernsea High School, Hull Roadrooftop solarrooftop solar0.3approved, not builtupdated Jan 2026Oct 2025granted Dec 2025Jan 2026East Riding of Yorkshire1.2
Sand Le Mere Holiday Village, Southfield Lanerooftop solarrooftop solar0.3approved, not builtupdated Feb 2026Dec 2025granted Jan 2026Feb 2026East Riding of Yorkshire5.2
Priest Close, Burton Roadwind turbinewind turbine0.2approved, not builtupdated May 2026Feb 2026granted Mar 2026May 2026East Riding of Yorkshire8.4

Distance from the average position of the HU19 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm201101
Rooftop solar202000.6
Wind farm700320
Wind turbine101000.2

MW in pipeline: pending, approved and under-construction capacity.

How East Riding of Yorkshire decides solar, wind and battery applications

ApplicationsEast Riding of YorkshireUK
Decided applications (solar, wind, battery)14310,236
Refused26 (18%)19%
Solar refused1 of 5912%
Onshore wind refused24 of 6345%
Battery storage refused1 of 2116%
Median time from submission to decision18.9 weeks17.0 weeks
Appeals lodged / allowed4 / 10—

All projects in East Riding of Yorkshire

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near HU19, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.