Skeffling Wind Farm (11.5 MW)
Skeffling Wind Farm is an 11.5 MW wind farm project in East Riding of Yorkshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application withdrawn on 19 March 2015; the record was last updated on 28 May 2015.
11.5 MWwind farm
application withdrawnstatus in REPD
28 May 2015record last updated
East Riding of Yorkshirecouncil area
Planning timeline
| Date | Stage |
|---|---|
| 10 January 2012 | Application submitted |
| 19 March 2015 | Application withdrawn |
Project details
- Technology
- wind farm
- Capacity
- 11.5 MW
- Status (REPD)
- application withdrawn
- Record last updated
- 28 May 2015
- Operator or applicant
- BT - Wind for Change
- Planning authority
- East Riding of Yorkshire
- Planning application reference
- 11/05745/STPLFE
- Turbines
- 5
- Council area (by location)
- East Riding of Yorkshire
- REPD reference
- 4176
Who decides
| Applications | East Riding of Yorkshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 143 | 10,236 |
| Refused | 26 (18%) | 19% |
| Solar refused | 1 of 59 | 12% |
| Onshore wind refused | 24 of 63 | 45% |
| Battery storage refused | 1 of 21 | 16% |
| Median time from submission to decision | 18.9 weeks | 17.0 weeks |
| Appeals lodged / allowed | 4 / 10 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Out Newton Wind Farm | wind farm | 9 | operational | 1.0 |
| Eastfield Farm Wind Farm | wind farm | 11.4 | refused | 5.5 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.6604, 0.0958).