Tedder Hill Wind cluster (7.5 MW)

Tedder Hill Wind cluster is a 7.5 MW wind farm project in East Riding of Yorkshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 30 August 2013; the record was last updated on 6 March 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7.5 MWwind farm
operationalstatus in REPD
6 March 2014record last updated
East Riding of Yorkshirecouncil area

Planning timeline

DateStage
11 May 2006Application submitted
12 September 2008Refused by the planning authority
28 January 2010Planning permission granted
28 January 2010Appeal allowed
30 October 2012Construction started
30 August 2013Operational

Project details

Technology
wind farm
Capacity
7.5 MW
Status (REPD)
operational
Record last updated
6 March 2014
Operator or applicant
Ventient (formerly Infinis)
Planning authority
East Riding of Yorkshire
Planning application reference
06/03729/STPLF
Appeal reference
09/00029/REFUSE
Turbines
3
Address (REPD)
near Roos, East Riding of Yorkshire
Council area (by location)
East Riding of Yorkshire
Time to decision
194 weeks
REPD reference
3749

Who decides

ApplicationsEast Riding of YorkshireUK
Decided applications (solar, wind, battery)14310,236
Refused26 (18%)19%
Solar refused1 of 5912%
Onshore wind refused24 of 6345%
Battery storage refused1 of 2116%
Median time from submission to decision18.9 weeks17.0 weeks
Appeals lodged / allowed4 / 10—

Other large projects within 10 km

ProjectTypeMWStatuskm
Monkwith Wind Farmwind farm6.9refused on appeal1.6
Roos Wind Farm (Resubmission)wind farm17.1operational2.8
Burton Pidsea (Wadworth Hill) Wind Farmwind farm10.2operational5.7
Redhall Industrial Estatesolar farm5operational6.6
Eastfield Farm Wind Farmwind farm11.4refused7.6
Elstronwick, Burstwick - Daisy Hill Solar Photovoltaic Farmsolar farm35approved, not built7.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.7523, -0.0265).