Far Marsh Farm (7.5 MW wind farm)
Far Marsh Farm is a 7.5 MW wind farm project in East Riding of Yorkshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 15 January 2017; the record was last updated on 27 March 2017.
7.5 MWwind farm
operationalstatus in REPD
27 March 2017record last updated
East Riding of Yorkshirecouncil area
Planning timeline
| Date | Stage |
|---|---|
| 14 December 2012 | Application submitted |
| 24 December 2013 | Planning permission granted |
| 15 October 2016 | Construction started |
| 15 January 2017 | Operational |
Project details
- Technology
- wind farm
- Capacity
- 7.5 MW
- Status (REPD)
- operational
- Record last updated
- 27 March 2017
- Operator or applicant
- Private Developer
- Planning authority
- East Riding of Yorkshire
- Planning application reference
- 12/04962/STPLFE
- Turbines
- 3
- Address (REPD)
- Marsh Road, Ottringham, Hull,
- Council area (by location)
- East Riding of Yorkshire
- Time to decision
- 54 weeks
- REPD reference
- 4660
Earlier applications for this site
| Application | MW | Submitted | Outcome |
|---|---|---|---|
| Far Marsh Farm 11/05896/STPLFE | 7.5 | 3 January 2012 | withdrawn 4 April 2012 |
Who decides
| Applications | East Riding of Yorkshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 143 | 10,236 |
| Refused | 26 (18%) | 19% |
| Solar refused | 1 of 59 | 12% |
| Onshore wind refused | 24 of 63 | 45% |
| Battery storage refused | 1 of 21 | 16% |
| Median time from submission to decision | 18.9 weeks | 17.0 weeks |
| Appeals lodged / allowed | 4 / 10 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Redhall Industrial Estate | solar farm | 5 | operational | 3.9 |
| Burton Pidsea (Wadworth Hill) Wind Farm | wind farm | 10.2 | operational | 8.0 |
| Europa Way | battery storage | 80 | approved, not built | 8.4 |
| Elstronwick, Burstwick - Daisy Hill Solar Photovoltaic Farm | solar farm | 35 | approved, not built | 8.5 |
| Harbour Farm Solar Farm | solar farm | 42 | application submitted | 8.6 |
| Netherlands Way Battery Energy Facility | battery storage | 80 | approved, not built | 8.6 |
| Roos Wind Farm (Resubmission) | wind farm | 17.1 | operational | 8.8 |
| Stallingborough Wind farm | wind farm | 6 | application withdrawn | 9.0 |
| Trondheim Way | battery storage | 5 | approved, not built | 9.0 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.6775, -0.1141).