Far Marsh Farm (7.5 MW wind farm)

Far Marsh Farm is a 7.5 MW wind farm project in East Riding of Yorkshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 15 January 2017; the record was last updated on 27 March 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7.5 MWwind farm
operationalstatus in REPD
27 March 2017record last updated
East Riding of Yorkshirecouncil area

Planning timeline

DateStage
14 December 2012Application submitted
24 December 2013Planning permission granted
15 October 2016Construction started
15 January 2017Operational

Project details

Technology
wind farm
Capacity
7.5 MW
Status (REPD)
operational
Record last updated
27 March 2017
Operator or applicant
Private Developer
Planning authority
East Riding of Yorkshire
Planning application reference
12/04962/STPLFE
Turbines
3
Address (REPD)
Marsh Road, Ottringham, Hull,
Council area (by location)
East Riding of Yorkshire
Time to decision
54 weeks
REPD reference
4660

Earlier applications for this site

ApplicationMWSubmittedOutcome
Far Marsh Farm 11/05896/STPLFE7.53 January 2012withdrawn 4 April 2012

Who decides

ApplicationsEast Riding of YorkshireUK
Decided applications (solar, wind, battery)14310,236
Refused26 (18%)19%
Solar refused1 of 5912%
Onshore wind refused24 of 6345%
Battery storage refused1 of 2116%
Median time from submission to decision18.9 weeks17.0 weeks
Appeals lodged / allowed4 / 10—

Other large projects within 10 km

ProjectTypeMWStatuskm
Redhall Industrial Estatesolar farm5operational3.9
Burton Pidsea (Wadworth Hill) Wind Farmwind farm10.2operational8.0
Europa Waybattery storage80approved, not built8.4
Elstronwick, Burstwick - Daisy Hill Solar Photovoltaic Farmsolar farm35approved, not built8.5
Harbour Farm Solar Farmsolar farm42application submitted8.6
Netherlands Way Battery Energy Facilitybattery storage80approved, not built8.6
Roos Wind Farm (Resubmission)wind farm17.1operational8.8
Stallingborough Wind farmwind farm6application withdrawn9.0
Trondheim Waybattery storage5approved, not built9.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.6775, -0.1141).