Energy Projects Near You

Trondheim Way (5 MW battery storage)

Trondheim Way is a 5 MW battery storage project in North East Lincolnshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 5 April 2022, not yet built; the record was last updated on 25 March 2022. REPD also records that the planning permission expired on 5 April 2025, so the project may not go ahead in this form. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWbattery storage
approved, not builtmay be out of datestatus in REPD
25 March 2022record last updated
North East Lincolnshirecouncil area

REPD also records that the planning permission expired on 5 April 2025, so the project may not go ahead in this form.

Planning timeline

DateStage
7 March 2022Application submitted
5 April 2022Planning permission granted
5 April 2025Permission expired

Project details

Technology
battery storage (stand-alone storage)
Capacity
5 MW
Status (REPD)
approved, not built
Record last updated
25 March 2022
Operator or applicant
Vox Energy Limited
Planning authority
North East Lincolnshire
Planning application reference
DM/1158/21/FUL
Address (REPD)
Trondheim Way, Stallingborough, Grimsby
Council area (by location)
North East Lincolnshire
Time to decision
4 weeks
Name in REPD
Trondheim Way - Battery Storage Facility
REPD reference
10872

Who decides

ApplicationsNorth East LincolnshireUK
Decided applications (solar, wind, battery)4110,236
Refused2 (5%)19%
Solar refused1 of 3012%
Onshore wind refused0 of 245%
Battery storage refused1 of 916%
Median time from submission to decision17.6 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Trondheim Way Battery energy storagebattery storage80under construction<0.1
Netherlands Way Battery Energy Facilitybattery storage80approved, not built0.4
Europa Waybattery storage80approved, not built0.7
Stallingborough Wind farmwind farm6application withdrawn1.0
Mauxhall Farmsolar farm18permission expired1.4
Mauxhall Farmbattery storage24permission expired1.4
Solar Farm at Adj To A180solar farm49.9approved, not built1.6
Immingham Solar Farmbattery storage30approved, not built1.6
Stallingboroughe, Stallingborough Road Solar PV Energysolar farm37.4approved, not built2.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.6065, -0.1802).