Solar, wind and battery projects near Grimsby (DN41)
50 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of DN41 (North East Lincolnshire): 6 are waiting for a planning decision, 33 approved but not yet running, 4 operational. The largest live scheme is Sweetbriar Farm (800 MW battery storage, application submitted on 2 July 2025, no decision recorded), 8.5 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of DN41
Projects of 1 MW and more (31)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Stallingborough Roadbattery storage | battery storage | 125 | application submittedupdated Aug 2025 | Jul 2025 | — | Aug 2025 | North East Lincolnshire | 0.7 |
| Stallingborough Roadsolar farm | solar farm | 12.4 | application submittedupdated Aug 2025 | Jul 2025 | — | Aug 2025 | North East Lincolnshire | 0.7 |
| Mauxhall Farmbattery storage | battery storage | 24 | permission expiredupdated Feb 2021 | Dec 2019 | granted May 2021 | Feb 2021 | North East Lincolnshire | 2.3 |
| Mauxhall Farmsolar farm | solar farm | 18 | permission expiredupdated Feb 2021 | Dec 2019 | granted May 2020 | Feb 2021 | North East Lincolnshire | 2.3 |
| Grimsby Solar Farmsolar farm | solar farm | 49.9 | under constructionupdated Oct 2025 | Oct 2021 | granted Nov 2022 | Oct 2025 | North East Lincolnshire | 2.7 |
| Solar Farm at Adj To A180solar farm | solar farm | 49.9 | approved, not builtupdated May 2025 | Feb 2024 | granted May 2025 | May 2025 | North East Lincolnshire | 2.9 |
| Immingham Solar Farmbattery storage | battery storage | 30 | approved, not builtupdated May 2025 | Feb 2024 | granted May 2025 | May 2025 | North East Lincolnshire | 2.9 |
| Trondheim Way Battery energy storagebattery storage | battery storage | 80 | under constructionupdated May 2021 | Feb 2021 | granted Jan 2023 | May 2021 | North East Lincolnshire | 3.0 |
| Trondheim Waybattery storage | battery storage | 5 | approved, not built may be out of dateupdated Mar 2022 | Mar 2022 | granted Apr 2022 | Mar 2022 | North East Lincolnshire | 3.0 |
| Stallingborough Wind farmwind farm | wind farm | 6 | application withdrawnupdated Aug 2012 | Jul 2008 | — | Aug 2012 | North East Lincolnshire | 3.0 |
| Stallingboroughe, Stallingborough Roadbattery storage | battery storage | 375 | approved, not builtupdated Jun 2026 | Jun 2025 | granted Apr 2026 | Jun 2026 | North East Lincolnshire | 3.3 |
| Stallingboroughe, Stallingborough Road Solar PV Energysolar farm | solar farm | 37.4 | approved, not builtupdated Jun 2026 | Jun 2025 | granted Apr 2026 | Jun 2026 | North East Lincolnshire | 3.3 |
| Netherlands Way Battery Energy Facilitybattery storage | battery storage | 80 | approved, not built may be out of dateupdated Jan 2022 | Aug 2021 | granted Jan 2022 | Jan 2022 | North East Lincolnshire | 3.4 |
| Europa Waybattery storage | battery storage | 80 | approved, not builtupdated Jun 2025 | Nov 2024 | granted May 2025 | Jun 2025 | North East Lincolnshire | 3.6 |
| HSH Coldstores, Estate Roadrooftop solar | rooftop solar | 1.1 | operationalupdated Jan 2024 | Mar 2023 | granted May 2023 | Jan 2024 | North East Lincolnshire | 4.9 |
| Port Of Immingham West Riverside, Immingham Dockswind turbine | wind turbine | 4.2 | approved, not builtupdated May 2026 | Apr 2024 | granted Mar 2026 | May 2026 | North East Lincolnshire | 5.2 |
| Port Of Immingham West Riverside, Immingham Dockswind turbine | wind turbine | 4.2 | approved, not builtupdated Jan 2026 | May 2024 | granted Dec 2025 | Jan 2026 | North East Lincolnshire | 5.2 |
| Shed 10, Alexandra Road South, Immingham Docksrooftop solar | rooftop solar | 1.4 | approved, not builtupdated Sep 2023 | Jul 2023 | granted Sep 2023 | Sep 2023 | North East Lincolnshire | 5.2 |
| Shed 27, Alexandra Road, South Imminghamrooftop solar | rooftop solar | 1.1 | approved, not builtupdated Sep 2023 | Jul 2023 | granted Sep 2023 | Sep 2023 | North East Lincolnshire | 5.2 |
| West Marsh (Phase 1)solar farm | solar farm | 2 | abandonedupdated Jan 2019 | Oct 2014 | granted Feb 2015 | Jan 2019 | North East Lincolnshire | 5.8 |
| Macaulay Lane Solar Farmsolar farm | solar farm | 8 | application withdrawnupdated Sep 2022 | May 2021 | — | Sep 2022 | North East Lincolnshire | 5.9 |
| West Marsh (Phase 2)solar farm | solar farm | 5 | abandonedupdated Jan 2019 | Oct 2014 | granted Feb 2015 | Jan 2019 | North East Lincolnshire | 5.9 |
| Magnolia Streetbattery storage | battery storage | 20 | abandonedupdated Mar 2019 | Sep 2017 | — | Mar 2019 | North East Lincolnshire | 6.0 |
| Bradley Road Solar Farmsolar farm | solar farm | 43.7 | approved, not builtupdated May 2024 | Nov 2023 | granted Apr 2024 | May 2024 | North East Lincolnshire | 6.1 |
| Bradley Roadbattery storage | battery storage | 10 | approved, not builtupdated May 2024 | Nov 2023 | granted Apr 2024 | May 2024 | North East Lincolnshire | 6.1 |
| Grimsby West, Birchin Wayrooftop solar | rooftop solar | 1.1 | operationalupdated Jan 2024 | Mar 2023 | granted May 2023 | Jan 2024 | North East Lincolnshire | 6.3 |
| Low Farm Solar Arraysolar farm | solar farm | 20 | operationalupdated Jan 2024 | Jun 2015 | granted Oct 2015 | Jan 2024 | North East Lincolnshire | 6.7 |
| Laceby Solar Farmsolar farm | solar farm | 27.1 | operationalupdated Jul 2016 | Mar 2015 | granted Jun 2015 | Jul 2016 | North East Lincolnshire | 7.0 |
| Gorton Street & Murray Street, Grimsby Dockssolar farm | solar farm | 1.5 | approved, not builtupdated Jul 2025 | Mar 2025 | granted Jul 2025 | Jul 2025 | North East Lincolnshire | 8.4 |
| Sweetbriar Farmbattery storage | battery storage | 800 | application submittedupdated Aug 2025 | Jul 2025 | — | Aug 2025 | North Lincolnshire | 8.5 |
| Sweet Briar Farm Solar Farmsolar farm | solar farm | 39 | approved, not builtupdated May 2026 | Feb 2022 | granted Feb 2024 | May 2026 | North Lincolnshire | 9.1 |
Smaller schemes under 1 MW, mostly rooftop solar (19)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Abp Border Control Post Building, Queens Road Solar Photovoltaic Panelrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Oct 2023 | Aug 2023 | granted Oct 2023 | Oct 2023 | North East Lincolnshire | 4.2 |
| Innovation Centrerooftop solar | rooftop solar | — | application submitted may be out of dateupdated Jan 2022 | Dec 2021 | — | Jan 2022 | North East Lincolnshire | 4.3 |
| Daniels Chilled Foods, Lakesiderooftop solar | rooftop solar | 0.8 | approved, not builtupdated Aug 2025 | Jun 2025 | granted Jul 2025 | Aug 2025 | North East Lincolnshire | 4.5 |
| Harvest Pet Products Limitedrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jul 2022 | Jun 2022 | granted Aug 2022 | Jul 2022 | West Lindsey | 4.6 |
| Hilmore Road, Laceby - Photovoltaic Solar Systemrooftop solar | rooftop solar | 0.5 | approved, not builtupdated Mar 2022 | Feb 2022 | granted May 2022 | Mar 2022 | North East Lincolnshire | 5.0 |
| Armadillo Self Storage, The Deans, 1 Estate Roadrooftop solar | rooftop solar | 0.1 | approved, not builtupdated Jul 2025 | May 2025 | granted Jun 2025 | Jul 2025 | North East Lincolnshire | 5.2 |
| Estate Roadrooftop solar | rooftop solar | 0.7 | approved, not built may be out of dateupdated Apr 2022 | Mar 2022 | granted May 2022 | Apr 2022 | North East Lincolnshire | 5.2 |
| Freshney Green Primary Care Centre, Sorrel Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated May 2024 | Mar 2024 | granted May 2024 | May 2024 | North East Lincolnshire | 5.7 |
| Estuary Waywind turbine | wind turbine | — | application submitted may be out of dateupdated May 2024 | Apr 2024 | — | May 2024 | North East Lincolnshire | 6.5 |
| Manor Golf Course, Barton Streetsolar farm | solar farm | — | approved, not builtupdated Oct 2024 | Mar 2024 | granted Sep 2024 | Oct 2024 | North East Lincolnshire | 6.5 |
| ABP Immingham, Shed 35 Immingham Dockrooftop solar | rooftop solar | 0.5 | approved, not builtupdated May 2023 | Mar 2023 | granted Apr 2023 | May 2023 | North Lincolnshire | 6.6 |
| Gleadell Bulk Terminal, Alexandra Road Southrooftop solar | rooftop solar | 0.8 | approved, not builtupdated Apr 2023 | Feb 2023 | granted Apr 2023 | Apr 2023 | North Lincolnshire | 6.9 |
| Vpi Power Station, Rosper Road, South Killingholmebattery storage | battery storage | — | approved, not builtupdated Jul 2022 | Jul 2022 | granted Aug 2022 | Jul 2022 | North Lincolnshire | 6.9 |
| J Sainsbury Plc, Corporation Roadrooftop solar | rooftop solar | 0.5 | application submitted | Jun 2026 | — | — | North East Lincolnshire | 7.3 |
| Grimsby Institute, Laceby Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Nov 2022 | Sep 2022 | granted Nov 2022 | Nov 2022 | North East Lincolnshire | 7.4 |
| Diana Princess Of Wales Hospitalrooftop solar | rooftop solar | 0.8 | approved, not builtupdated Apr 2026 | Dec 2025 | granted Feb 2026 | Apr 2026 | North East Lincolnshire | 7.7 |
| Murray Street, Grimsby Dockssolar farm | solar farm | 0.8 | approved, not builtupdated Jul 2025 | Mar 2025 | granted Jul 2025 | Jul 2025 | North East Lincolnshire | 7.9 |
| N H Case Limitedrooftop solar | rooftop solar | 0.4 | under constructionupdated Nov 2021 | Sep 2021 | granted Aug 2022 | Nov 2021 | North East Lincolnshire | 8.3 |
| Oasis Academy Wintringhamrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jul 2022 | Feb 2020 | granted Mar 2020 | Jul 2022 | North East Lincolnshire | 8.4 |
Distance from the average position of the DN41 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 15 | 1 | 8 | 2 | 0 | 235 |
| Rooftop solar | 19 | 2 | 15 | 2 | 0 | 8.6 |
| Wind farm | 1 | 0 | 0 | 0 | 0 | 0 |
| Wind turbine | 3 | 1 | 2 | 0 | 0 | 8.4 |
| Battery storage | 12 | 2 | 8 | 0 | 0 | 1,585 |
MW in pipeline: pending, approved and under-construction capacity.
How North East Lincolnshire decides solar, wind and battery applications
| Applications | North East Lincolnshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 41 | 10,236 |
| Refused | 2 (5%) | 19% |
| Solar refused | 1 of 30 | 12% |
| Onshore wind refused | 0 of 2 | 45% |
| Battery storage refused | 1 of 9 | 16% |
| Median time from submission to decision | 17.6 weeks | 17.0 weeks |
| Appeals lodged / allowed | 0 / 0 | — |
All projects in North East Lincolnshire
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near DN41, 5 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.