Energy Projects Near You

Laceby Solar Farm (27.1 MW)

Laceby Solar Farm is a 27.1 MW solar farm project in North East Lincolnshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 22 June 2016; the record was last updated on 14 July 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

27.1 MWsolar farm
operationalstatus in REPD
14 July 2016record last updated
North East Lincolnshirecouncil area

Planning timeline

DateStage
5 March 2015Application submitted
19 June 2015Planning permission granted
15 April 2016Construction started
22 June 2016Operational

Project details

Technology
solar farm
Capacity
27.1 MW
Status (REPD)
operational
Record last updated
14 July 2016
Operator or applicant
Conergy
Planning authority
North East Lincolnshire
Planning application reference
DM/0174/15/FUL
Site area
36.5 ha
Address (REPD)
Land At Manor Top Farm Manor Top Farm Access Road To Laceby
Council area (by location)
North East Lincolnshire
Time to decision
15 weeks
REPD reference
4880

Who decides

ApplicationsNorth East LincolnshireUK
Decided applications (solar, wind, battery)4110,236
Refused2 (5%)19%
Solar refused1 of 3012%
Onshore wind refused0 of 245%
Battery storage refused1 of 916%
Median time from submission to decision17.6 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Low Farm Solar Arraysolar farm20operational1.2
Bradley Roadbattery storage10approved, not built2.8
Bradley Road Solar Farmsolar farm43.7approved, not built2.8
Grimsby Solar Farmsolar farm49.9under construction4.3
Magnolia Streetbattery storage20abandoned5.1
West Marsh (Phase 2)solar farm5abandoned5.8
Macaulay Lane Solar Farmsolar farm8application withdrawn5.8
Gunnerby Road - 30MW Battery Energy Storagebattery storage30application submitted6.0
Hewitts Avenue, New Walthambattery storage49.9approved, not built6.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.5251, -0.1461).