Energy Projects Near You

Bradley Road (10 MW battery storage)

Bradley Road is a 10 MW battery storage project in North East Lincolnshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 26 April 2024, not yet built; the record was last updated on 3 May 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10 MWbattery storage
approved, not builtstatus in REPD
3 May 2024record last updated
North East Lincolnshirecouncil area

Planning timeline

DateStage
28 November 2023Application submitted
26 April 2024Planning permission granted
26 April 2027Permission due to expire (unless work starts)

Project details

Technology
battery storage (co-located with re)
Capacity
10 MW
Status (REPD)
approved, not built
Record last updated
3 May 2024
Operator or applicant
Renewable Connections Developments Limited
Planning authority
North East Lincolnshire
Planning application reference
DM/1156/23/FUL
Address (REPD)
W/O Bradley Road, Grimsby
Council area (by location)
North East Lincolnshire
Time to decision
21 weeks
Name in REPD
Bradley Road - Battery Energy Storage System
REPD reference
13863

Recorded together with Bradley Road Solar Farm (43.7 MW solar farm, approved, not built).

Who decides

ApplicationsNorth East LincolnshireUK
Decided applications (solar, wind, battery)4110,236
Refused2 (5%)19%
Solar refused1 of 3012%
Onshore wind refused0 of 245%
Battery storage refused1 of 916%
Median time from submission to decision17.6 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Low Farm Solar Arraysolar farm20operational1.6
Magnolia Streetbattery storage20abandoned2.3
Laceby Solar Farmsolar farm27.1operational2.8
West Marsh (Phase 2)solar farm5abandoned3.0
Macaulay Lane Solar Farmsolar farm8application withdrawn3.0
Grimsby Solar Farmsolar farm49.9under construction3.7
Hewitts Avenue, New Walthambattery storage49.9approved, not built5.0
Stallingborough Roadsolar farm12.4application submitted6.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.5465, -0.1228).