Sweet Briar Farm Solar Farm (39 MW)

Sweet Briar Farm Solar Farm is a 39 MW solar farm project in North Lincolnshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 9 February 2024, not yet built; the record was last updated on 8 May 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

39 MWsolar farm
approved, not builtstatus in REPD
8 May 2026record last updated
North Lincolnshirecouncil area

Planning timeline

DateStage
18 February 2022Application submitted
9 February 2024Planning permission granted
9 February 2029Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
39 MW
Status (REPD)
approved, not built
Record last updated
8 May 2026
Operator or applicant
Lightrock Power
Planning authority
North Lincolnshire
Planning application reference
PA/2022/443
Site area
69.7 ha
Address (REPD)
Sweet Briar Farm, Carr Road, Ulceby
Council area (by location)
North Lincolnshire
Time to decision
103 weeks
Name in REPD
Sweet Briar Farm - Solar Farm
REPD reference
9832

Who decides

ApplicationsNorth LincolnshireUK
Decided applications (solar, wind, battery)4710,236
Refused15 (32%)19%
Solar refused7 of 3312%
Onshore wind refused8 of 1045%
Battery storage refused0 of 416%
Median time from submission to decision10.0 weeks17.0 weeks
Appeals lodged / allowed6 / 4—

Other large projects within 10 km

ProjectTypeMWStatuskm
Sweetbriar Farmbattery storage800application submitted0.6
Stallingboroughe, Stallingborough Roadbattery storage375approved, not built6.2
Stallingboroughe, Stallingborough Road Solar PV Energysolar farm37.4approved, not built6.2
Elsham Wind Farmwind farm30refused on appeal6.2
Solar Farm at Adj To A180solar farm49.9approved, not built7.2
Immingham Solar Farmbattery storage30approved, not built7.2
Mauxhall Farmbattery storage24permission expired7.7
Mauxhall Farmsolar farm18permission expired7.7
Wren Kitchens & Bedrooms, Parrott Streetrooftop solar6.6under construction8.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.6266, -0.3091).