Mauxhall Farm (24 MW battery storage)

Mauxhall Farm is a 24 MW battery storage project in North East Lincolnshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: planning permission expired on 6 November 2023; the record was last updated on 7 February 2021.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

24 MWbattery storage
permission expiredstatus in REPD
7 February 2021record last updated
North East Lincolnshirecouncil area

Planning timeline

DateStage
17 December 2019Application submitted
6 November 2020Refused by the planning authority
21 May 2021Planning permission granted
6 November 2023Permission expired

Project details

Technology
battery storage (co-located with re)
Capacity
24 MW
Status (REPD)
permission expired
Record last updated
7 February 2021
Operator or applicant
ENGIE Renewables
Planning authority
North East Lincolnshire
Planning application reference
DM/1145/19/FUL
Address (REPD)
Mauxhall Farm, Immingham Road, Stallingborough, Grimsby, Humberside
Council area (by location)
North East Lincolnshire
Time to decision
74 weeks
REPD reference
7827

Who decides

ApplicationsNorth East LincolnshireUK
Decided applications (solar, wind, battery)4110,236
Refused2 (5%)19%
Solar refused1 of 3012%
Onshore wind refused0 of 245%
Battery storage refused1 of 916%
Median time from submission to decision17.6 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Mauxhall Farmsolar farm18permission expired<0.1
Immingham Solar Farmbattery storage30approved, not built0.6
Solar Farm at Adj To A180solar farm49.9approved, not built0.6
Trondheim Way Battery energy storagebattery storage80under construction1.4
Trondheim Waybattery storage5approved, not built1.4
Stallingboroughe, Stallingborough Roadbattery storage375approved, not built1.5
Stallingboroughe, Stallingborough Road Solar PV Energysolar farm37.4approved, not built1.5
Netherlands Way Battery Energy Facilitybattery storage80approved, not built1.7
Europa Waybattery storage80approved, not built2.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.6019, -0.2).