Stallingboroughe, Stallingborough Road Solar PV Energy (37.4 MW)
Stallingboroughe, Stallingborough Road Solar PV Energy is a 37.4 MW solar farm project in North East Lincolnshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 24 April 2026, not yet built; the record was last updated on 9 June 2026.
37.4 MWsolar farm
approved, not builtstatus in REPD
9 June 2026record last updated
North East Lincolnshirecouncil area
Planning timeline
| Date | Stage |
|---|---|
| 30 June 2025 | Application submitted |
| 24 April 2026 | Planning permission granted |
| 24 April 2031 | Permission due to expire (unless work starts) |
Project details
- Technology
- solar farm
- Capacity
- 37.4 MW
- Status (REPD)
- approved, not built
- Record last updated
- 9 June 2026
- Operator or applicant
- Island Green Power
- Planning authority
- North East Lincolnshire
- Planning application reference
- DM/0455/25/FUL
- Site area
- 110.9 ha
- Address (REPD)
- W/O A1173 Stallingborough, E/O Stallingborough Road, Keelby, Grimsby
- Council area (by location)
- North East Lincolnshire
- Time to decision
- 43 weeks
- Name in REPD
- Stallingboroughe, Stallingborough Road - Solar PV Energy
- REPD reference
- 17458
Recorded together with Stallingboroughe, Stallingborough Road (375 MW battery storage, approved, not built).
Who decides
| Applications | North East Lincolnshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 41 | 10,236 |
| Refused | 2 (5%) | 19% |
| Solar refused | 1 of 30 | 12% |
| Onshore wind refused | 0 of 2 | 45% |
| Battery storage refused | 1 of 9 | 16% |
| Median time from submission to decision | 17.6 weeks | 17.0 weeks |
| Appeals lodged / allowed | 0 / 0 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Immingham Solar Farm | battery storage | 30 | approved, not built | 1.1 |
| Solar Farm at Adj To A180 | solar farm | 49.9 | approved, not built | 1.1 |
| Mauxhall Farm | solar farm | 18 | permission expired | 1.5 |
| Mauxhall Farm | battery storage | 24 | permission expired | 1.5 |
| Trondheim Way Battery energy storage | battery storage | 80 | under construction | 2.7 |
| Trondheim Way | battery storage | 5 | approved, not built | 2.7 |
| Netherlands Way Battery Energy Facility | battery storage | 80 | approved, not built | 2.9 |
| Stallingborough Road | solar farm | 12.4 | application submitted | 3.3 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.6064, -0.2217).