Energy Projects Near You

Solar Farm at Adj To A180 (49.9 MW)

Solar Farm at Adj To A180 is a 49.9 MW solar farm project in North East Lincolnshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 6 May 2025, not yet built; the record was last updated on 12 May 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
approved, not builtstatus in REPD
12 May 2025record last updated
North East Lincolnshirecouncil area

Planning timeline

DateStage
22 February 2024Application submitted
6 May 2025Planning permission granted

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
12 May 2025
Operator or applicant
One Planet Developments Limited
Planning authority
North East Lincolnshire
Planning application reference
DM/0108/24/FUL
Site area
109.5 ha
Address (REPD)
Adj To A180, To S/O Immingham, Immingham
Council area (by location)
North East Lincolnshire
Time to decision
63 weeks
Name in REPD
Immingham Solar Farm - Solar Farm
REPD reference
16091

Who decides

ApplicationsNorth East LincolnshireUK
Decided applications (solar, wind, battery)4110,236
Refused2 (5%)19%
Solar refused1 of 3012%
Onshore wind refused0 of 245%
Battery storage refused1 of 916%
Median time from submission to decision17.6 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Immingham Solar Farmbattery storage30approved, not built<0.1
Mauxhall Farmsolar farm18permission expired0.6
Mauxhall Farmbattery storage24permission expired0.6
Stallingboroughe, Stallingborough Road Solar PV Energysolar farm37.4approved, not built1.1
Stallingboroughe, Stallingborough Roadbattery storage375approved, not built1.1
Trondheim Way Battery energy storagebattery storage80under construction1.6
Trondheim Waybattery storage5approved, not built1.6
Netherlands Way Battery Energy Facilitybattery storage80approved, not built1.8
Europa Waybattery storage80approved, not built2.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.6067, -0.2049).