Stallingboroughe, Stallingborough Road (375 MW battery storage)

Stallingboroughe, Stallingborough Road is a 375 MW battery storage project in North East Lincolnshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 24 April 2026, not yet built; the record was last updated on 9 June 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

375 MWbattery storage
approved, not builtstatus in REPD
9 June 2026record last updated
North East Lincolnshirecouncil area

Planning timeline

DateStage
30 June 2025Application submitted
24 April 2026Planning permission granted
24 April 2031Permission due to expire (unless work starts)

Project details

Technology
battery storage (co-located with re)
Capacity
375 MW
Status (REPD)
approved, not built
Record last updated
9 June 2026
Operator or applicant
Island Green Power
Planning authority
North East Lincolnshire
Planning application reference
DM/0455/25/FUL
Address (REPD)
W/O A1173 Stallingborough, E/O Stallingborough Road, Keelby, Grimsby
Council area (by location)
North East Lincolnshire
Time to decision
43 weeks
Name in REPD
Stallingboroughe, Stallingborough Road - BESS
REPD reference
17459

Recorded together with Stallingboroughe, Stallingborough Road Solar PV Energy (37.4 MW solar farm, approved, not built).

Who decides

ApplicationsNorth East LincolnshireUK
Decided applications (solar, wind, battery)4110,236
Refused2 (5%)19%
Solar refused1 of 3012%
Onshore wind refused0 of 245%
Battery storage refused1 of 916%
Median time from submission to decision17.6 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Immingham Solar Farmbattery storage30approved, not built1.1
Solar Farm at Adj To A180solar farm49.9approved, not built1.1
Mauxhall Farmsolar farm18permission expired1.5
Mauxhall Farmbattery storage24permission expired1.5
Trondheim Way Battery energy storagebattery storage80under construction2.7
Trondheim Waybattery storage5approved, not built2.7
Netherlands Way Battery Energy Facilitybattery storage80approved, not built2.9
Stallingborough Roadsolar farm12.4application submitted3.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.6064, -0.2217).