Solar, wind and battery projects near Ulceby (DN39)
25 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of DN39 (North Lincolnshire): 3 are waiting for a planning decision, 18 approved but not yet running. The largest live scheme is Sweetbriar Farm (800 MW battery storage, application submitted on 2 July 2025, no decision recorded), 2.2 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of DN39
Projects of 1 MW and more (17)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Sweet Briar Farm Solar Farmsolar farm | solar farm | 39 | approved, not builtupdated May 2026 | Feb 2022 | granted Feb 2024 | May 2026 | North Lincolnshire | 2.1 |
| Sweetbriar Farmbattery storage | battery storage | 800 | application submittedupdated Aug 2025 | Jul 2025 | — | Aug 2025 | North Lincolnshire | 2.2 |
| Elsham Wind Farmwind farm | wind farm | 30 | refused on appealupdated Nov 2006 | Aug 2004 | refused Jun 2005 | Nov 2006 | North Lincolnshire | 4.3 |
| Stallingboroughe, Stallingborough Roadbattery storage | battery storage | 375 | approved, not builtupdated Jun 2026 | Jun 2025 | granted Apr 2026 | Jun 2026 | North East Lincolnshire | 7.6 |
| Stallingboroughe, Stallingborough Road Solar PV Energysolar farm | solar farm | 37.4 | approved, not builtupdated Jun 2026 | Jun 2025 | granted Apr 2026 | Jun 2026 | North East Lincolnshire | 7.6 |
| Wren Kitchens & Bedrooms, Parrott Streetrooftop solar | rooftop solar | 6.6 | under construction | — | — | — | North Lincolnshire | 8.4 |
| Solar Farm at Adj To A180solar farm | solar farm | 49.9 | approved, not builtupdated May 2025 | Feb 2024 | granted May 2025 | May 2025 | North East Lincolnshire | 8.7 |
| Immingham Solar Farmbattery storage | battery storage | 30 | approved, not builtupdated May 2025 | Feb 2024 | granted May 2025 | May 2025 | North East Lincolnshire | 8.7 |
| Mauxhall Farmbattery storage | battery storage | 24 | permission expiredupdated Feb 2021 | Dec 2019 | granted May 2021 | Feb 2021 | North East Lincolnshire | 9.1 |
| Mauxhall Farmsolar farm | solar farm | 18 | permission expiredupdated Feb 2021 | Dec 2019 | granted May 2020 | Feb 2021 | North East Lincolnshire | 9.1 |
| Saxby Wold Wind Farmwind farm | wind farm | 36 | refused on appealupdated Sep 2014 | Jun 2011 | refused Feb 2012 | Sep 2014 | North Lincolnshire | 9.1 |
| Stallingborough Roadbattery storage | battery storage | 125 | application submittedupdated Aug 2025 | Jul 2025 | — | Aug 2025 | North East Lincolnshire | 9.6 |
| Stallingborough Roadsolar farm | solar farm | 12.4 | application submittedupdated Aug 2025 | Jul 2025 | — | Aug 2025 | North East Lincolnshire | 9.6 |
| Port Of Immingham West Riverside, Immingham Dockswind turbine | wind turbine | 4.2 | approved, not builtupdated May 2026 | Apr 2024 | granted Mar 2026 | May 2026 | North East Lincolnshire | 9.9 |
| Port Of Immingham West Riverside, Immingham Dockswind turbine | wind turbine | 4.2 | approved, not builtupdated Jan 2026 | May 2024 | granted Dec 2025 | Jan 2026 | North East Lincolnshire | 9.9 |
| Shed 10, Alexandra Road South, Immingham Docksrooftop solar | rooftop solar | 1.4 | approved, not builtupdated Sep 2023 | Jul 2023 | granted Sep 2023 | Sep 2023 | North East Lincolnshire | 9.9 |
| Shed 27, Alexandra Road, South Imminghamrooftop solar | rooftop solar | 1.1 | approved, not builtupdated Sep 2023 | Jul 2023 | granted Sep 2023 | Sep 2023 | North East Lincolnshire | 9.9 |
Smaller schemes under 1 MW, mostly rooftop solar (8)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Agrimin Limited, Schiphol Wayrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jul 2023 | Apr 2023 | granted May 2023 | Jul 2023 | North Lincolnshire | 3.7 |
| Gleadell Bulk Terminal, Alexandra Road Southrooftop solar | rooftop solar | 0.8 | approved, not builtupdated Apr 2023 | Feb 2023 | granted Apr 2023 | Apr 2023 | North Lincolnshire | 4.8 |
| Dodds Wold Farm, Elshamrooftop solar | rooftop solar | 0.1 | approved, not builtupdated Aug 2025 | Jun 2025 | granted Jul 2025 | Aug 2025 | North Lincolnshire | 5.4 |
| Elsham Wold Industrial Estaterooftop solar | rooftop solar | 0.3 | approved, not builtupdated May 2022 | Apr 2022 | granted Jun 2022 | May 2022 | North Lincolnshire | 5.4 |
| Elsham Wold Industrial Estate, Pegasus Roadrooftop solar | rooftop solar | 0.3 | approved, not builtupdated May 2022 | Apr 2022 | granted Jun 2022 | May 2022 | North Lincolnshire | 5.6 |
| Vpi Power Station, Rosper Road, South Killingholmebattery storage | battery storage | — | approved, not builtupdated Jul 2022 | Jul 2022 | granted Aug 2022 | Jul 2022 | North Lincolnshire | 7.2 |
| ABP Immingham, Shed 35 Immingham Dockrooftop solar | rooftop solar | 0.5 | approved, not builtupdated May 2023 | Mar 2023 | granted Apr 2023 | May 2023 | North Lincolnshire | 8.6 |
| Harvest Pet Products Limitedrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jul 2022 | Jun 2022 | granted Aug 2022 | Jul 2022 | West Lindsey | 8.9 |
Distance from the average position of the DN39 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 5 | 1 | 3 | 0 | 0 | 139 |
| Rooftop solar | 10 | 0 | 10 | 0 | 0 | 11.5 |
| Wind farm | 2 | 0 | 0 | 0 | 2 | 0 |
| Wind turbine | 2 | 0 | 2 | 0 | 0 | 8.4 |
| Battery storage | 6 | 2 | 3 | 0 | 0 | 1,330 |
MW in pipeline: pending, approved and under-construction capacity.
How North Lincolnshire decides solar, wind and battery applications
| Applications | North Lincolnshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 47 | 10,236 |
| Refused | 15 (32%) | 19% |
| Solar refused | 7 of 33 | 12% |
| Onshore wind refused | 8 of 10 | 45% |
| Battery storage refused | 0 of 4 | 16% |
| Median time from submission to decision | 10.0 weeks | 17.0 weeks |
| Appeals lodged / allowed | 6 / 4 | — |
All projects in North Lincolnshire
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.