Energy Projects Near You

Sweetbriar Farm (800 MW battery storage)

Sweetbriar Farm is an 800 MW battery storage project in North Lincolnshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 2 July 2025, no decision recorded; the record was last updated on 8 August 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

800 MWbattery storage
application submittedstatus in REPD
8 August 2025record last updated
North Lincolnshirecouncil area

Planning timeline

DateStage
2 July 2025Application submitted

Project details

Technology
battery storage (stand-alone storage)
Capacity
800 MW
Status (REPD)
application submitted
Record last updated
8 August 2025
Operator or applicant
Lightrock Power Limited
Planning authority
North Lincolnshire
Planning application reference
PA/2025/794
Address (REPD)
S/O Sweetbriar Farm, Ulceby
Council area (by location)
North Lincolnshire
Name in REPD
Sweetbriar Farm - Battery Energy Storage System
REPD reference
18069

Who decides

ApplicationsNorth LincolnshireUK
Decided applications (solar, wind, battery)4710,236
Refused15 (32%)19%
Solar refused7 of 3312%
Onshore wind refused8 of 1045%
Battery storage refused0 of 416%
Median time from submission to decision10.0 weeks17.0 weeks
Appeals lodged / allowed6 / 4—

Other large projects within 10 km

ProjectTypeMWStatuskm
Sweet Briar Farm Solar Farmsolar farm39approved, not built0.6
Stallingboroughe, Stallingborough Road Solar PV Energysolar farm37.4approved, not built5.7
Stallingboroughe, Stallingborough Roadbattery storage375approved, not built5.7
Elsham Wind Farmwind farm30refused on appeal6.5
Solar Farm at Adj To A180solar farm49.9approved, not built6.7
Immingham Solar Farmbattery storage30approved, not built6.7
Mauxhall Farmsolar farm18permission expired7.2
Mauxhall Farmbattery storage24permission expired7.2
Stallingborough Roadsolar farm12.4application submitted8.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.6222, -0.3036).