Mauxhall Farm (18 MW solar farm)
Mauxhall Farm is an 18 MW solar farm project in North East Lincolnshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: planning permission expired on 6 November 2023; the record was last updated on 7 February 2021.
18 MWsolar farm
permission expiredstatus in REPD
7 February 2021record last updated
North East Lincolnshirecouncil area
Planning timeline
| Date | Stage |
|---|---|
| 17 December 2019 | Application submitted |
| 28 May 2020 | Planning permission granted |
| 6 November 2023 | Permission expired |
Project details
- Technology
- solar farm
- Capacity
- 18 MW
- Status (REPD)
- permission expired
- Record last updated
- 7 February 2021
- Operator or applicant
- ENGIE Renewables
- Planning authority
- North East Lincolnshire
- Planning application reference
- DM/1145/19/FUL
- Site area
- 47.2 ha
- Address (REPD)
- Mauxhall Farm, Immingham Road, Stallingborough, Grimsby, Humberside
- Council area (by location)
- North East Lincolnshire
- Time to decision
- 23 weeks
- REPD reference
- 7221
Who decides
| Applications | North East Lincolnshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 41 | 10,236 |
| Refused | 2 (5%) | 19% |
| Solar refused | 1 of 30 | 12% |
| Onshore wind refused | 0 of 2 | 45% |
| Battery storage refused | 1 of 9 | 16% |
| Median time from submission to decision | 17.6 weeks | 17.0 weeks |
| Appeals lodged / allowed | 0 / 0 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Mauxhall Farm | battery storage | 24 | permission expired | <0.1 |
| Immingham Solar Farm | battery storage | 30 | approved, not built | 0.6 |
| Solar Farm at Adj To A180 | solar farm | 49.9 | approved, not built | 0.6 |
| Trondheim Way Battery energy storage | battery storage | 80 | under construction | 1.4 |
| Trondheim Way | battery storage | 5 | approved, not built | 1.4 |
| Stallingboroughe, Stallingborough Road | battery storage | 375 | approved, not built | 1.5 |
| Stallingboroughe, Stallingborough Road Solar PV Energy | solar farm | 37.4 | approved, not built | 1.5 |
| Netherlands Way Battery Energy Facility | battery storage | 80 | approved, not built | 1.7 |
| Europa Way | battery storage | 80 | approved, not built | 2.1 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.6019, -0.2).