Solar, wind and battery projects near Barton-upon-Humber (DN18)
25 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of DN18 (North Lincolnshire): 1 is waiting for a planning decision, 18 approved but not yet running, 4 operational. The largest live scheme is Humberfield Recycling Centre (30 MW battery storage, approved on 28 July 2025, not yet built), 4.8 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of DN18
Projects of 1 MW and more (12)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Wren Kitchens & Bedrooms, Parrott Streetrooftop solar | rooftop solar | 6.6 | under construction | — | — | — | North Lincolnshire | 2.8 |
| Saxby Wold Wind Farmwind farm | wind farm | 36 | refused on appealupdated Sep 2014 | Jun 2011 | refused Feb 2012 | Sep 2014 | North Lincolnshire | 4.4 |
| Humberfield Recycling Centrebattery storage | battery storage | 30 | approved, not builtupdated Nov 2025 | May 2025 | granted Jul 2025 | Nov 2025 | East Riding of Yorkshire | 4.8 |
| Bayram Timber Limited, Gibson Lane Southrooftop solar | rooftop solar | 1.7 | approved, not builtupdated May 2026 | Feb 2026 | granted Apr 2026 | May 2026 | East Riding of Yorkshire | 6.8 |
| Melton Waste Parkwind farm | wind farm | 5 | operationalupdated Jun 2017 | Feb 2015 | granted Apr 2015 | Jun 2017 | East Riding of Yorkshire | 6.9 |
| Melton Common Wind Clusterwind farm | wind farm | 5 | operationalupdated Sep 2023 | Jun 2013 | granted Dec 2013 | Sep 2023 | East Riding of Yorkshire | 7.0 |
| Melton Common Wind Clusterwind turbine | wind turbine | 2.3 | approved, not built may be out of dateupdated Sep 2023 | Jun 2014 | granted Feb 2016 | Sep 2023 | East Riding of Yorkshire | 7.3 |
| Melton Common Wind Clusterwind farm | wind farm | 4.6 | application submitted may be out of dateupdated Sep 2023 | Aug 2023 | — | Sep 2023 | East Riding of Yorkshire | 7.5 |
| Meltonwind farm | wind farm | 3 | approved, not builtupdated Jan 2025 | May 2022 | granted Feb 2024 | Jan 2025 | East Riding of Yorkshire | 7.7 |
| Elsham Wind Farmwind farm | wind farm | 30 | refused on appealupdated Nov 2006 | Aug 2004 | refused Jun 2005 | Nov 2006 | North Lincolnshire | 7.9 |
| Carr Lane Solar Farmsolar farm | solar farm | 9 | approved, not builtupdated Aug 2023 | Jul 2021 | granted Aug 2023 | Aug 2023 | North Lincolnshire | 8.5 |
| Cottingham Solar Farmsolar farm | solar farm | 5 | operationalupdated May 2022 | Jun 2021 | granted Mar 2022 | May 2022 | East Riding of Yorkshire | 9.9 |
Smaller schemes under 1 MW, mostly rooftop solar (13)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Luxinar Limited, Rofin Houserooftop solar | rooftop solar | 0.4 | approved, not builtupdated May 2023 | Feb 2023 | granted Apr 2023 | May 2023 | East Riding of Yorkshire | 5.0 |
| Spire Hospital, Lowfield Roadrooftop solar | rooftop solar | 0.3 | approved, not builtupdated May 2024 | Mar 2024 | granted Apr 2024 | May 2024 | East Riding of Yorkshire | 6.5 |
| Melton Enterprise Park, Redcliff Roadrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Apr 2026 | Dec 2025 | granted Feb 2026 | Apr 2026 | East Riding of Yorkshire | 7.0 |
| XPO UK Supply Chain Limited, Salvesen Wayrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Jan 2025 | Oct 2024 | granted Dec 2024 | Jan 2025 | Kingston upon Hull | 7.1 |
| Cranswick Foods, William Wright Dockrooftop solar | rooftop solar | 0.6 | approved, not builtupdated Jun 2026 | Dec 2025 | granted Feb 2026 | Jun 2026 | Kingston upon Hull | 7.7 |
| Andrew Johnson Knudtzon Limited, Boulevardrooftop solar | rooftop solar | 0.7 | approved, not builtupdated Feb 2024 | Dec 2023 | granted Feb 2024 | Feb 2024 | Kingston upon Hull | 8.1 |
| Andrew Johnson Knudtzonrooftop solar | rooftop solar | 0.5 | approved, not builtupdated Dec 2021 | Oct 2021 | granted Dec 2021 | Dec 2021 | Kingston upon Hull | 8.1 |
| Elsham Wold Industrial Estate, Pegasus Roadrooftop solar | rooftop solar | 0.3 | approved, not builtupdated May 2022 | Apr 2022 | granted Jun 2022 | May 2022 | North Lincolnshire | 8.3 |
| Elsham Wold Industrial Estaterooftop solar | rooftop solar | 0.3 | approved, not builtupdated May 2022 | Apr 2022 | granted Jun 2022 | May 2022 | North Lincolnshire | 8.3 |
| Dodds Wold Farm, Elshamrooftop solar | rooftop solar | 0.1 | approved, not builtupdated Aug 2025 | Jun 2025 | granted Jul 2025 | Aug 2025 | North Lincolnshire | 8.6 |
| Smith And Nephew, Hessle Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Aug 2025 | May 2025 | granted Jul 2025 | Aug 2025 | Kingston upon Hull | 8.8 |
| Hull Royal Infirmaryrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Feb 2026 | Nov 2025 | granted Jan 2026 | Feb 2026 | Kingston upon Hull | 9.1 |
| Samaritans Spring Bank Solar Panelsrooftop solar | rooftop solar | — | operationalupdated Feb 2024 | Dec 2020 | granted Mar 2021 | Feb 2024 | Kingston upon Hull | 9.9 |
Distance from the average position of the DN18 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 2 | 0 | 1 | 1 | 0 | 9 |
| Rooftop solar | 15 | 0 | 14 | 1 | 0 | 12.6 |
| Wind farm | 6 | 1 | 1 | 2 | 2 | 7.6 |
| Wind turbine | 1 | 0 | 1 | 0 | 0 | 2.3 |
| Battery storage | 1 | 0 | 1 | 0 | 0 | 30 |
MW in pipeline: pending, approved and under-construction capacity.
How North Lincolnshire decides solar, wind and battery applications
| Applications | North Lincolnshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 47 | 10,236 |
| Refused | 15 (32%) | 19% |
| Solar refused | 7 of 33 | 12% |
| Onshore wind refused | 8 of 10 | 45% |
| Battery storage refused | 0 of 4 | 16% |
| Median time from submission to decision | 10.0 weeks | 17.0 weeks |
| Appeals lodged / allowed | 6 / 4 | — |
All projects in North Lincolnshire
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near DN18, 2 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.