Energy Projects Near You

Solar, wind and battery projects near North Ferriby (HU14)

32 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of HU14 (East Riding of Yorkshire): 1 is waiting for a planning decision, 19 approved but not yet running, 6 operational. The largest live scheme is Creyke Beck Substation Solar Farm & Battery Storage (49.9 MW solar farm, approved on 6 January 2022, not yet built; REPD status may be out of date), 7.9 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

32projects within 10 km
1awaiting a decision
19approved, not running
6operational

Projects within 10 km of HU14

Projects of 1 MW and more (18)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Meltonwind farmwind farm3approved, not builtupdated Jan 2025May 2022granted Feb 2024Jan 2025East Riding of Yorkshire1.6
Melton Waste Parkwind farmwind farm5operationalupdated Jun 2017Feb 2015granted Apr 2015Jun 2017East Riding of Yorkshire2.5
Humberfield Recycling Centrebattery storagebattery storage30approved, not builtupdated Nov 2025May 2025granted Jul 2025Nov 2025East Riding of Yorkshire2.6
Melton Common Wind Clusterwind farmwind farm4.6application submitted may be out of dateupdated Sep 2023Aug 2023—Sep 2023East Riding of Yorkshire2.7
Melton Common Wind Clusterwind turbinewind turbine2.3approved, not built may be out of dateupdated Sep 2023Jun 2014granted Feb 2016Sep 2023East Riding of Yorkshire2.9
Melton Common Wind Clusterwind farmwind farm5operationalupdated Sep 2023Jun 2013granted Dec 2013Sep 2023East Riding of Yorkshire3.0
Bayram Timber Limited, Gibson Lane Southrooftop solarrooftop solar1.7approved, not builtupdated May 2026Feb 2026granted Apr 2026May 2026East Riding of Yorkshire3.1
Cottingham Solar Farmsolar farmsolar farm5operationalupdated May 2022Jun 2021granted Mar 2022May 2022East Riding of Yorkshire5.7
Creyke Beck Substation Solar Farm & Battery Storagesolar farmsolar farm49.9approved, not built may be out of dateupdated Feb 2024Aug 2021granted Jan 2022Feb 2024East Riding of Yorkshire7.9
Snuff Mill Lane Gates Solar Farm & Battery Storagesolar farmsolar farm9.7application withdrawnupdated Mar 2024Aug 2023—Mar 2024East Riding of Yorkshire8.2
Wren Kitchens & Bedrooms, Parrott Streetrooftop solarrooftop solar6.6under construction———North Lincolnshire8.3
Bagletts Wind Farmwind farmwind farm6.9application withdrawnupdated Aug 2015Dec 2014—Aug 2015East Riding of Yorkshire8.6
Croxby Hall Farm, Inglemire Lane Solar Farm & Battery Storagesolar farmsolar farm9.7application withdrawnupdated Mar 2024Aug 2023—Mar 2024East Riding of Yorkshire9.0
Carr Lane Solar Farmsolar farmsolar farm9approved, not builtupdated Aug 2023Jul 2021granted Aug 2023Aug 2023North Lincolnshire9.3
Creyke Beckbattery storagebattery storage49.9operationalupdated Jan 2019Apr 2017granted Jun 2017Jan 2019East Riding of Yorkshire9.3
Saxby Wold Wind Farmwind farmwind farm36refused on appealupdated Sep 2014Jun 2011refused Feb 2012Sep 2014North Lincolnshire9.7
Pillswood Phase 1battery storagebattery storage49.5operationalupdated Nov 2022Apr 2017granted Oct 2018Nov 2022East Riding of Yorkshire9.8
Pillswood Phase 2battery storagebattery storage49.5operationalupdated Nov 2022May 2019granted Jul 2023Nov 2022East Riding of Yorkshire9.9
Smaller schemes under 1 MW, mostly rooftop solar (14)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Melton Enterprise Park, Redcliff Roadrooftop solarrooftop solar0.3approved, not builtupdated Apr 2026Dec 2025granted Feb 2026Apr 2026East Riding of Yorkshire1.9
Luxinar Limited, Rofin Houserooftop solarrooftop solar0.4approved, not builtupdated May 2023Feb 2023granted Apr 2023May 2023East Riding of Yorkshire2.6
Braffords Farm, Riplingham Roadwind turbinewind turbine0.3approved, not builtupdated Aug 2024Dec 2023granted Jul 2024Aug 2024East Riding of Yorkshire4.1
Spire Hospital, Lowfield Roadrooftop solarrooftop solar0.3approved, not builtupdated May 2024Mar 2024granted Apr 2024May 2024East Riding of Yorkshire4.5
Creyke Beck Substationbattery storagebattery storage—approved, not builtupdated Feb 2024Dec 2023granted Mar 2024Feb 2024East Riding of Yorkshire7.9
XPO UK Supply Chain Limited, Salvesen Wayrooftop solarrooftop solar0.4approved, not builtupdated Jan 2025Oct 2024granted Dec 2024Jan 2025Kingston upon Hull8.1
Snuff Mill Lane Gates Solar Farm & Battery Storagebattery storagebattery storage—application withdrawnupdated Mar 2024Aug 2023—Mar 2024East Riding of Yorkshire8.2
Cottingham Water Pumping Station, Mill Housesolar farmsolar farm0.4approved, not builtupdated Oct 2023Jun 2023granted Sep 2023Oct 2023East Riding of Yorkshire8.6
Croxby Hall Farm, Inglemire Lane Solar Farm & Battery Storagebattery storagebattery storage—application withdrawnupdated Mar 2024Aug 2023—Mar 2024East Riding of Yorkshire9.0
Cranswick Foods, William Wright Dockrooftop solarrooftop solar0.6approved, not builtupdated Jun 2026Dec 2025granted Feb 2026Jun 2026Kingston upon Hull9.0
Andrew Johnson Knudtzon Limited, Boulevardrooftop solarrooftop solar0.7approved, not builtupdated Feb 2024Dec 2023granted Feb 2024Feb 2024Kingston upon Hull9.2
Andrew Johnson Knudtzonrooftop solarrooftop solar0.5approved, not builtupdated Dec 2021Oct 2021granted Dec 2021Dec 2021Kingston upon Hull9.2
Hull Royal Infirmaryrooftop solarrooftop solar0.2approved, not builtupdated Feb 2026Nov 2025granted Jan 2026Feb 2026Kingston upon Hull9.5
Smith And Nephew, Hessle Roadrooftop solarrooftop solar0.2approved, not builtupdated Aug 2025May 2025granted Jul 2025Aug 2025Kingston upon Hull9.7

Distance from the average position of the HU14 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm6031059.3
Rooftop solar110110011.8
Wind farm611217.6
Wind turbine202002.6
Battery storage7023030

MW in pipeline: pending, approved and under-construction capacity.

How East Riding of Yorkshire decides solar, wind and battery applications

ApplicationsEast Riding of YorkshireUK
Decided applications (solar, wind, battery)14310,236
Refused26 (18%)19%
Solar refused1 of 5912%
Onshore wind refused24 of 6345%
Battery storage refused1 of 2116%
Median time from submission to decision18.9 weeks17.0 weeks
Appeals lodged / allowed4 / 10—

All projects in East Riding of Yorkshire

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near HU14, 3 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.