Energy Projects Near You

Carr Lane Solar Farm (9 MW)

Carr Lane Solar Farm is a 9 MW solar farm project in North Lincolnshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 7 August 2023, not yet built; the record was last updated on 15 August 2023.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

9 MWsolar farm
approved, not builtstatus in REPD
15 August 2023record last updated
North Lincolnshirecouncil area

Planning timeline

DateStage
26 July 2021Application submitted
3 November 2022Refused by the planning authority
21 February 2023Appeal lodged
7 August 2023Planning permission granted
7 August 2023Appeal allowed
7 August 2026Permission expired

Project details

Technology
solar farm
Capacity
9 MW
Status (REPD)
approved, not built
Record last updated
15 August 2023
Operator or applicant
Anesco Limited
Planning authority
North Lincolnshire
Planning application reference
PA/2021/1359
Appeal reference
APP/Y2003/W/23/3317097
Site area
14.0 ha
Address (REPD)
S/O Carr Lane, Winterton, Scunthorpe
Council area (by location)
North Lincolnshire
Time to decision
106 weeks
Name in REPD
Carr Lane - Solar Farm
REPD reference
9004

Who decides

ApplicationsNorth LincolnshireUK
Decided applications (solar, wind, battery)4710,236
Refused15 (32%)19%
Solar refused7 of 3312%
Onshore wind refused8 of 1045%
Battery storage refused0 of 416%
Median time from submission to decision10.0 weeks17.0 weeks
Appeals lodged / allowed6 / 4—

Other large projects within 10 km

ProjectTypeMWStatuskm
Winterton Road, Roxby Solar Farmsolar farm50application submitted3.7
Ironstone Quarry Wind Farmwind farm7.5refused3.8
Winterton Landfill Site - Ground Mounted Solar PV Arrayssolar farm5under construction4.8
Melton Common Wind Clusterwind farm5operational6.8
Saxby Wold Wind Farmwind farm36refused on appeal6.9
Bagmoorwind farm16operational7.2
Melton Waste Parkwind farm5operational7.2
Winterton Roadbattery storage95approved, not built8.1
Grangewind farm12.3operational8.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.6555, -0.5683).