Winterton Road (95 MW battery storage)

Winterton Road is a 95 MW battery storage project in North Lincolnshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 16 December 2022, not yet built; the record was last updated on 15 September 2021. REPD also records that the planning permission expired on 16 December 2025, so the project may not go ahead in this form. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

95 MWbattery storage
approved, not builtmay be out of datestatus in REPD
15 September 2021record last updated
North Lincolnshirecouncil area

REPD also records that the planning permission expired on 16 December 2025, so the project may not go ahead in this form.

Planning timeline

DateStage
12 August 2021Application submitted
16 December 2022Planning permission granted
16 December 2025Permission expired

Project details

Technology
battery storage (stand-alone storage)
Capacity
95 MW
Status (REPD)
approved, not built
Record last updated
15 September 2021
Operator or applicant
Newton Energi Limited
Planning authority
North Lincolnshire
Planning application reference
PA/2021/1291
Address (REPD)
N/O Gala Bingo, Winterton Road, Scunthorpe
Council area (by location)
North Lincolnshire
Time to decision
70 weeks
Name in REPD
Winterton Road - Battery Energy Storage
REPD reference
9608

Who decides

ApplicationsNorth LincolnshireUK
Decided applications (solar, wind, battery)4710,236
Refused15 (32%)19%
Solar refused7 of 3312%
Onshore wind refused8 of 1045%
Battery storage refused0 of 416%
Median time from submission to decision10.0 weeks17.0 weeks
Appeals lodged / allowed6 / 4—

Other large projects within 10 km

ProjectTypeMWStatuskm
Little Crow Solar Parksolar farm150approved, not built2.7
Bagmoorwind farm16operational3.8
Flixborough Industrial Estatesolar farm5operational4.4
North Wharf Solar Farmsolar farm6refused on appeal4.4
North Lincolnshire Green Energy Parkbattery storage30approved, not built4.7
Winterton Road, Roxby Solar Farmsolar farm50application submitted5.0
Raventhorpe Lodge (Sweeting Thorns)solar farm25permission expired5.1
Raventhorpe Farmsolar farm38operational5.7
Grangewind farm12.3operational6.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.5972, -0.6412).