Energy Projects Near You

North Lincolnshire Green Energy Park (30 MW)

North Lincolnshire Green Energy Park is a 30 MW battery storage project in North Lincolnshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 13 March 2025, not yet built; the record was last updated on 18 March 2025. As a nationally significant project, it was decided by the Secretary of State for Energy Security and Net Zero on a Development Consent Order after examination by the Planning Inspectorate (EN010116).

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

30 MWbattery storage
approved, not builtstatus in REPD
18 March 2025record last updated
North Lincolnshirecouncil area

Planning timeline

DateStage
31 May 2022Application submitted
13 March 2025Development consent granted (Secretary of State)

Project details

Technology
battery storage (co-located with re)
Capacity
30 MW
Status (REPD)
approved, not built
Record last updated
18 March 2025
Operator or applicant
Solar 21 Renewable Energy Limited
Planning authority
The Planning Inspectorate - National Infrastructure
Planning application reference
EN010116
Address (REPD)
Flixborough Wharf, Flixborough Industrial Estate, Scunthorpe
Council area (by location)
North Lincolnshire
Time to decision
145 weeks
REPD reference
12706

Official project record at the Planning Inspectorate (EN010116)

Who decides

As a nationally significant project, it was decided by the Secretary of State for Energy Security and Net Zero on a Development Consent Order after examination by the Planning Inspectorate (EN010116). All Energy Secretary decisions on solar and wind farms. The Planning Inspectorate - National Infrastructure refused 7% of 46 decided solar, wind and battery applications in REPD (median 73 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Flixborough Industrial Estatesolar farm5operational0.4
North Wharf Solar Farmsolar farm6refused on appeal0.4
Grangewind farm12.3operational2.0
Bagmoorwind farm16operational2.4
North Moor Farm, Keadbysolar farm49.9application submitted2.6
Keadby Wind Farmwind farm68operational4.2
Winterton Roadbattery storage95approved, not built4.7
Solar Farm at Ealand Roadsolar farm49.9application submitted6.0
Winterton Road, Roxby Solar Farmsolar farm50application submitted6.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.6198, -0.7012).