Grange (12.3 MW wind farm)

Grange is a 12.3 MW wind farm project in North Lincolnshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 15 December 2015; the record was last updated on 31 July 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

12.3 MWwind farm
operationalstatus in REPD
31 July 2017record last updated
North Lincolnshirecouncil area

Planning timeline

DateStage
2 November 2010Application submitted
6 April 2011Refused by the planning authority
7 January 2014Planning permission granted
7 January 2014Appeal allowed
1 January 2015Construction started
15 December 2015Operational

Project details

Technology
wind farm
Capacity
12.3 MW
Status (REPD)
operational
Record last updated
31 July 2017
Operator or applicant
Octopus Investements/Blue Energy
Planning authority
North Lincolnshire
Planning application reference
WF/2010/1242
Turbines
6
Address (REPD)
Grange Farmhouse, Land adjacent to, Flixborough
Council area (by location)
North Lincolnshire
Time to decision
166 weeks
REPD reference
4069

Earlier applications for this site

ApplicationMWSubmittedOutcome
Flixborough Grange Farmhouse WF/2009/05731411 May 2009refused 29 January 2010

Who decides

ApplicationsNorth LincolnshireUK
Decided applications (solar, wind, battery)4710,236
Refused15 (32%)19%
Solar refused7 of 3312%
Onshore wind refused8 of 1045%
Battery storage refused0 of 416%
Median time from submission to decision10.0 weeks17.0 weeks
Appeals lodged / allowed6 / 4—

Other large projects within 10 km

ProjectTypeMWStatuskm
Flixborough Industrial Estatesolar farm5operational2.0
North Wharf Solar Farmsolar farm6refused on appeal2.0
North Lincolnshire Green Energy Parkbattery storage30approved, not built2.0
Bagmoorwind farm16operational2.4
North Moor Farm, Keadbysolar farm49.9application submitted3.8
Keadby Wind Farmwind farm68operational5.1
Winterton Road, Roxby Solar Farmsolar farm50application submitted5.5
Ironstone Quarry Wind Farmwind farm7.5refused5.9
Winterton Roadbattery storage95approved, not built6.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.6379, -0.7001).