Energy Projects Near You

Solar, wind and battery projects near Scunthorpe (DN16)

41 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of DN16 (North Lincolnshire): 10 are waiting for a planning decision, 20 approved but not yet running, 6 operational. The largest live scheme is Little Crow Solar Park (150 MW solar farm, approved on 5 April 2022, not yet built), 1.7 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

41projects within 10 km
10awaiting a decision
20approved, not running
6operational

Projects within 10 km of DN16

Projects of 1 MW and more (23)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Little Crow Solar Parksolar farmsolar farm150approved, not builtupdated Apr 2022Dec 2020granted Apr 2022Apr 2022North Lincolnshire1.7
Raventhorpe Lodge (Sweeting Thorns)solar farmsolar farm25permission expiredupdated Sep 2020Feb 2015granted Dec 2016Sep 2020North Lincolnshire2.7
Church Lane Solar Canopyrooftop solarrooftop solar1.1approved, not builtupdated Jul 2025Apr 2025granted May 2025Jul 2025North Lincolnshire2.8
Bradken UKwind turbinewind turbine2.5refusedupdated Jul 2014May 2011refused Aug 2011Jul 2014North Lincolnshire3.2
Winterton Roadbattery storagebattery storage95approved, not built may be out of dateupdated Sep 2021Aug 2021granted Dec 2022Sep 2021North Lincolnshire3.3
Raventhorpe Farmsolar farmsolar farm38operationalupdated Dec 2015Aug 2014granted Nov 2014Dec 2015North Lincolnshire3.9
Little Crow Solar Parkbattery storagebattery storage90approved, not builtupdated Apr 2025Dec 2020granted Apr 2022Apr 2025North Lincolnshire4.4
Manton Manor Solar Farmsolar farmsolar farm27refused on appealupdated Jul 2016Apr 2015refused Nov 2015Jul 2016North Lincolnshire5.9
Co-Op Nisa, Waldo Wayrooftop solarrooftop solar1.2approved, not builtupdated Jun 2026Mar 2026granted May 2026Jun 2026North Lincolnshire6.0
Sofina Distribution Centre, Normanby Enterprise Parkrooftop solarrooftop solar1.1approved, not builtupdated May 2025Apr 2025granted Apr 2025May 2025North Lincolnshire6.1
North Wharf Solar Farmsolar farmsolar farm6refused on appealupdated Nov 2016Sep 2015refused Nov 2015Nov 2016North Lincolnshire6.9
Flixborough Industrial Estatesolar farmsolar farm5operationalupdated May 2017Apr 2015granted Oct 2016May 2017North Lincolnshire6.9
Bagmoorwind farmwind farm16operationalupdated Aug 2012Jan 2005granted Apr 2006Aug 2012North Lincolnshire6.9
North Lincolnshire Green Energy Parkbattery storagebattery storage30approved, not builtupdated Mar 2025May 2022granted Mar 2025Mar 2025North Lincolnshire7.1
Sand Lane Solar Farmsolar farmsolar farm20.2application submittedupdated Jul 2025Jun 2025—Jul 2025North Lincolnshire7.5
Winterton Road, Roxby Solar Farmsolar farmsolar farm50application submitted may be out of dateupdated Feb 2024Feb 2024—Feb 2024North Lincolnshire8.1
North Moor Farm, Keadbysolar farmsolar farm49.9application submittedupdated Oct 2025Aug 2025—Oct 2025North Lincolnshire8.4
Grangewind farmwind farm12.3operationalupdated Jul 2017Nov 2010granted Jan 2014Jul 2017North Lincolnshire8.8
Scawby Roadsolar farmsolar farm49.9application submittedupdated May 2025Apr 2025—May 2025North Lincolnshire9.2
Scawby Roadbattery storagebattery storage30application submittedupdated May 2025Apr 2025—May 2025North Lincolnshire9.2
Scawby Brook, Briggbattery storagebattery storage99approved, not builtupdated Oct 2021Jul 2021granted Sep 2021Oct 2021North Lincolnshire9.3
Keadby Wind Farmwind farmwind farm68operationalupdated Feb 2015Oct 2003granted Feb 2008Feb 2015North Lincolnshire9.6
Solar Farm at Ealand Roadsolar farmsolar farm49.9application submittedupdated Sep 2025Aug 2025—Sep 2025North Lincolnshire9.6
Smaller schemes under 1 MW, mostly rooftop solar (18)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Frederick Gough School, Grange Lane Southrooftop solarrooftop solar0.2approved, not builtupdated Jan 2023Oct 2022granted Nov 2022Jan 2023North Lincolnshire0.8
Lakeside Retail Parkrooftop solarrooftop solar0.2approved, not builtupdated Apr 2026Dec 2025granted Jan 2026Apr 2026North Lincolnshire1.5
WM Morrison Supermarkets Solar Photovoltaicsrooftop solarrooftop solar0.6approved, not builtupdated Apr 2022Apr 2022granted Jun 2022Apr 2022North Lincolnshire1.7
John Leggott College, West Common Lanerooftop solarrooftop solar0.3approved, not builtupdated May 2023May 2023granted Jun 2023May 2023North Lincolnshire2.1
Baths Hall, Doncaster Roadrooftop solarrooftop solar0.2approved, not builtupdated Nov 2023Sep 2023granted Nov 2023Nov 2023North Lincolnshire2.9
Scunthorpe General Hospital, Cliff Gardensrooftop solarrooftop solar0.3application submittedupdated Dec 2025Dec 2025—Dec 2025North Lincolnshire2.9
Scunthorpe General Hospital, Cliff Gardensrooftop solarrooftop solar0.2approved, not builtupdated Jun 2026Mar 2026granted Apr 2026Jun 2026North Lincolnshire2.9
Scunthorpe General Hospital, Cliff Gardens Solar Canopysolar farmsolar farm0.2approved, not builtupdated Apr 2026Dec 2025granted Jan 2026Apr 2026North Lincolnshire2.9
Scunthorpe General Hospital, Cliff Gardensrooftop solarrooftop solar0.1application submittedupdated Oct 2025Sep 2025—Oct 2025North Lincolnshire2.9
Osi Food Solutions Factorysolar farmsolar farm0.7permission expiredupdated Jun 2020Sep 2019granted Jan 2020Jun 2020North Lincolnshire4.8
Foxhills Industrial Estatewind turbinewind turbine—application submittedupdated Jan 2026Dec 2025—Jan 2026North Lincolnshire5.1
The Range, Holyrood Driverooftop solarrooftop solar0.3approved, not builtupdated Jun 2026Mar 2026granted Apr 2026Jun 2026North Lincolnshire5.2
Sofina Scunthorpe, Billet Lanerooftop solarrooftop solar0.7approved, not builtupdated Jun 2025Apr 2025granted May 2025Jun 2025North Lincolnshire5.5
Pumping Station, Normanby Road - Micro Energy Storage Facilitybattery storagebattery storage0.2application submittedupdated Dec 2025Nov 2025—Dec 2025North Lincolnshire5.8
Chapel Lane Energy storage facilitybattery storagebattery storage—approved, not builtupdated Dec 2025Jan 2023granted Jan 2024Dec 2025North Lincolnshire7.5
Quinton And Kaines, Enterprise Courtrooftop solarrooftop solar0.5approved, not builtupdated May 2023Feb 2023granted Mar 2023May 2023North Lincolnshire9.2
Atherton Wayrooftop solarrooftop solar0.2operationalupdated May 2022Apr 2022granted Mar 2023May 2022North Lincolnshire9.4
The Vale Academy, Atherton Wayrooftop solarrooftop solar0.2approved, not builtupdated Jan 2026Oct 2025granted Jan 2026Jan 2026North Lincolnshire9.4

Distance from the average position of the DN16 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm135222370
Rooftop solar16213107.3
Wind farm300300
Wind turbine210010
Battery storage72500344

MW in pipeline: pending, approved and under-construction capacity.

How North Lincolnshire decides solar, wind and battery applications

ApplicationsNorth LincolnshireUK
Decided applications (solar, wind, battery)4710,236
Refused15 (32%)19%
Solar refused7 of 3312%
Onshore wind refused8 of 1045%
Battery storage refused0 of 416%
Median time from submission to decision10.0 weeks17.0 weeks
Appeals lodged / allowed6 / 4—

All projects in North Lincolnshire

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near DN16, 2 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.