Raventhorpe Lodge (Sweeting Thorns) (25 MW solar farm)

Raventhorpe Lodge (Sweeting Thorns) is a 25 MW solar farm project in North Lincolnshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: planning permission expired on 5 December 2019; the record was last updated on 23 September 2020.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

25 MWsolar farm
permission expiredstatus in REPD
23 September 2020record last updated
North Lincolnshirecouncil area

Planning timeline

DateStage
12 February 2015Application submitted
18 November 2015Refused by the planning authority
11 May 2016Appeal lodged
5 December 2016Planning permission granted
5 December 2016Appeal allowed
5 December 2019Permission expired

Project details

Technology
solar farm
Capacity
25 MW
Status (REPD)
permission expired
Record last updated
23 September 2020
Operator or applicant
Wirsol / Elgar Middleton
Planning authority
North Lincolnshire
Planning application reference
PA/2015/0114
Appeal reference
APP/Y2003/W/16/3145863
Address (REPD)
Raventhorpe Lodge, Storage Lan, Brigg Road, Access Road In Raventhorpe Lod, Scunthorpe, Humberside
Council area (by location)
North Lincolnshire
Time to decision
95 weeks
REPD reference
5013

Who decides

ApplicationsNorth LincolnshireUK
Decided applications (solar, wind, battery)4710,236
Refused15 (32%)19%
Solar refused7 of 3312%
Onshore wind refused8 of 1045%
Battery storage refused0 of 416%
Median time from submission to decision10.0 weeks17.0 weeks
Appeals lodged / allowed6 / 4—

Other large projects within 10 km

ProjectTypeMWStatuskm
Raventhorpe Farmsolar farm38operational1.4
Little Crow Solar Parksolar farm150approved, not built2.4
Manton Manor Solar Farmsolar farm27refused on appeal4.4
Winterton Roadbattery storage95approved, not built5.1
Sand Lane Solar Farmsolar farm20.2application submitted6.2
Scawby Roadsolar farm49.9application submitted6.6
Scawby Brook, Briggbattery storage99approved, not built6.6
Bagmoorwind farm16operational8.9
Winterton Road, Roxby Solar Farmsolar farm50application submitted9.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.5574, -0.6023).