Bagmoor (16 MW wind farm)
Bagmoor is a 16 MW wind farm project in North Lincolnshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 July 2009; the record was last updated on 16 August 2012.
16 MWwind farm
operationalstatus in REPD
16 August 2012record last updated
North Lincolnshirecouncil area
Planning timeline
| Date | Stage |
|---|---|
| 15 January 2005 | Application submitted |
| 1 April 2006 | Planning permission granted |
| 1 July 2009 | Operational |
Project details
- Technology
- wind farm
- Capacity
- 16 MW
- Status (REPD)
- operational
- Record last updated
- 16 August 2012
- Operator or applicant
- Munich Re (previously Wind Prospect)
- Planning authority
- North Lincolnshire
- Planning application reference
- not recorded
- Turbines
- 8
- Address (REPD)
- 2km East of Flixborough
- Council area (by location)
- North Lincolnshire
- Time to decision
- 63 weeks
- REPD reference
- 2928
Who decides
| Applications | North Lincolnshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 47 | 10,236 |
| Refused | 15 (32%) | 19% |
| Solar refused | 7 of 33 | 12% |
| Onshore wind refused | 8 of 10 | 45% |
| Battery storage refused | 0 of 4 | 16% |
| Median time from submission to decision | 10.0 weeks | 17.0 weeks |
| Appeals lodged / allowed | 6 / 4 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| North Wharf Solar Farm | solar farm | 6 | refused on appeal | 2.0 |
| Flixborough Industrial Estate | solar farm | 5 | operational | 2.0 |
| North Lincolnshire Green Energy Park | battery storage | 30 | approved, not built | 2.4 |
| Grange | wind farm | 12.3 | operational | 2.4 |
| Winterton Road, Roxby Solar Farm | solar farm | 50 | application submitted | 3.6 |
| Winterton Road | battery storage | 95 | approved, not built | 3.8 |
| North Moor Farm, Keadby | solar farm | 49.9 | application submitted | 5.0 |
| Ironstone Quarry Wind Farm | wind farm | 7.5 | refused | 5.1 |
| Winterton Landfill Site - Ground Mounted Solar PV Arrays | solar farm | 5 | under construction | 5.8 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.6277, -0.6672).