Energy Projects Near You

Flixborough Industrial Estate (5 MW solar farm)

Flixborough Industrial Estate is a 5 MW solar farm project in North Lincolnshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 March 2017; the record was last updated on 3 May 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
3 May 2017record last updated
North Lincolnshirecouncil area

Planning timeline

DateStage
8 April 2015Application submitted
18 November 2015Refused by the planning authority
20 January 2016Appeal lodged
11 October 2016Planning permission granted
11 October 2016Appeal allowed
1 March 2017Construction started
1 March 2017Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
3 May 2017
Operator or applicant
NESF (formerly INRG Solar)
Planning authority
North Lincolnshire
Planning application reference
PA/2015/0434
Appeal reference
APP/Y2003/W/16/3142032
Site area
12.9 ha
Address (REPD)
Land adjacent to Flixborough Industrial Estate, Stather Road, Flixborough
Council area (by location)
North Lincolnshire
Time to decision
79 weeks
REPD reference
5204

Who decides

ApplicationsNorth LincolnshireUK
Decided applications (solar, wind, battery)4710,236
Refused15 (32%)19%
Solar refused7 of 3312%
Onshore wind refused8 of 1045%
Battery storage refused0 of 416%
Median time from submission to decision10.0 weeks17.0 weeks
Appeals lodged / allowed6 / 4—

Other large projects within 10 km

ProjectTypeMWStatuskm
North Wharf Solar Farmsolar farm6refused on appeal<0.1
North Lincolnshire Green Energy Parkbattery storage30approved, not built0.4
Bagmoorwind farm16operational2.0
Grangewind farm12.3operational2.0
North Moor Farm, Keadbysolar farm49.9application submitted3.1
Winterton Roadbattery storage95approved, not built4.4
Keadby Wind Farmwind farm68operational4.6
Winterton Road, Roxby Solar Farmsolar farm50application submitted5.6
Solar Farm at Ealand Roadsolar farm49.9application submitted6.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.6201, -0.6947).