Energy Projects Near You

Solar, wind and battery projects near Scunthorpe (DN15)

36 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of DN15 (North Lincolnshire): 7 are waiting for a planning decision, 19 approved but not yet running, 5 operational. The largest live scheme is Little Crow Solar Park (150 MW solar farm, approved on 5 April 2022, not yet built), 4.8 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

36projects within 10 km
7awaiting a decision
19approved, not running
5operational

Projects within 10 km of DN15

Projects of 1 MW and more (21)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Co-Op Nisa, Waldo Wayrooftop solarrooftop solar1.2approved, not builtupdated Jun 2026Mar 2026granted May 2026Jun 2026North Lincolnshire0.9
Sofina Distribution Centre, Normanby Enterprise Parkrooftop solarrooftop solar1.1approved, not builtupdated May 2025Apr 2025granted Apr 2025May 2025North Lincolnshire1.1
Bagmoorwind farmwind farm16operationalupdated Aug 2012Jan 2005granted Apr 2006Aug 2012North Lincolnshire1.8
Winterton Roadbattery storagebattery storage95approved, not built may be out of dateupdated Sep 2021Aug 2021granted Dec 2022Sep 2021North Lincolnshire2.1
North Wharf Solar Farmsolar farmsolar farm6refused on appealupdated Nov 2016Sep 2015refused Nov 2015Nov 2016North Lincolnshire2.9
Flixborough Industrial Estatesolar farmsolar farm5operationalupdated May 2017Apr 2015granted Oct 2016May 2017North Lincolnshire2.9
Bradken UKwind turbinewind turbine2.5refusedupdated Jul 2014May 2011refused Aug 2011Jul 2014North Lincolnshire3.1
North Lincolnshire Green Energy Parkbattery storagebattery storage30approved, not builtupdated Mar 2025May 2022granted Mar 2025Mar 2025North Lincolnshire3.3
Church Lane Solar Canopyrooftop solarrooftop solar1.1approved, not builtupdated Jul 2025Apr 2025granted May 2025Jul 2025North Lincolnshire3.4
Winterton Road, Roxby Solar Farmsolar farmsolar farm50application submitted may be out of dateupdated Feb 2024Feb 2024—Feb 2024North Lincolnshire3.6
Grangewind farmwind farm12.3operationalupdated Jul 2017Nov 2010granted Jan 2014Jul 2017North Lincolnshire4.1
Little Crow Solar Parkbattery storagebattery storage90approved, not builtupdated Apr 2025Dec 2020granted Apr 2022Apr 2025North Lincolnshire4.3
Little Crow Solar Parksolar farmsolar farm150approved, not builtupdated Apr 2022Dec 2020granted Apr 2022Apr 2022North Lincolnshire4.8
North Moor Farm, Keadbysolar farmsolar farm49.9application submittedupdated Oct 2025Aug 2025—Oct 2025North Lincolnshire5.8
Ironstone Quarry Wind Farmwind farmwind farm7.5refusedupdated Dec 2014May 2011refused Jun 2013Dec 2014North Lincolnshire5.9
Winterton Landfill Site - Ground Mounted Solar PV Arrayssolar farmsolar farm5under constructionupdated Dec 2022Mar 2021granted Jul 2021Dec 2022North Lincolnshire6.9
Carr Lane Solar Farmsolar farmsolar farm9approved, not builtupdated Aug 2023Jul 2021granted Aug 2023Aug 2023North Lincolnshire7.1
Raventhorpe Lodge (Sweeting Thorns)solar farmsolar farm25permission expiredupdated Sep 2020Feb 2015granted Dec 2016Sep 2020North Lincolnshire7.2
Keadby Wind Farmwind farmwind farm68operationalupdated Feb 2015Oct 2003granted Feb 2008Feb 2015North Lincolnshire7.4
Raventhorpe Farmsolar farmsolar farm38operationalupdated Dec 2015Aug 2014granted Nov 2014Dec 2015North Lincolnshire7.6
Solar Farm at Ealand Roadsolar farmsolar farm49.9application submittedupdated Sep 2025Aug 2025—Sep 2025North Lincolnshire8.7
Smaller schemes under 1 MW, mostly rooftop solar (15)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Foxhills Industrial Estatewind turbinewind turbine—application submittedupdated Jan 2026Dec 2025—Jan 2026North Lincolnshire0.4
Pumping Station, Normanby Road - Micro Energy Storage Facilitybattery storagebattery storage0.2application submittedupdated Dec 2025Nov 2025—Dec 2025North Lincolnshire0.6
Sofina Scunthorpe, Billet Lanerooftop solarrooftop solar0.7approved, not builtupdated Jun 2025Apr 2025granted May 2025Jun 2025North Lincolnshire0.7
The Range, Holyrood Driverooftop solarrooftop solar0.3approved, not builtupdated Jun 2026Mar 2026granted Apr 2026Jun 2026North Lincolnshire1.8
Osi Food Solutions Factorysolar farmsolar farm0.7permission expiredupdated Jun 2020Sep 2019granted Jan 2020Jun 2020North Lincolnshire2.0
Baths Hall, Doncaster Roadrooftop solarrooftop solar0.2approved, not builtupdated Nov 2023Sep 2023granted Nov 2023Nov 2023North Lincolnshire2.7
Scunthorpe General Hospital, Cliff Gardensrooftop solarrooftop solar0.3application submittedupdated Dec 2025Dec 2025—Dec 2025North Lincolnshire3.2
Scunthorpe General Hospital, Cliff Gardensrooftop solarrooftop solar0.2approved, not builtupdated Jun 2026Mar 2026granted Apr 2026Jun 2026North Lincolnshire3.2
Scunthorpe General Hospital, Cliff Gardens Solar Canopysolar farmsolar farm0.2approved, not builtupdated Apr 2026Dec 2025granted Jan 2026Apr 2026North Lincolnshire3.2
Scunthorpe General Hospital, Cliff Gardensrooftop solarrooftop solar0.1application submittedupdated Oct 2025Sep 2025—Oct 2025North Lincolnshire3.2
John Leggott College, West Common Lanerooftop solarrooftop solar0.3approved, not builtupdated May 2023May 2023granted Jun 2023May 2023North Lincolnshire4.6
Lakeside Retail Parkrooftop solarrooftop solar0.2approved, not builtupdated Apr 2026Dec 2025granted Jan 2026Apr 2026North Lincolnshire6.0
WM Morrison Supermarkets Solar Photovoltaicsrooftop solarrooftop solar0.6approved, not builtupdated Apr 2022Apr 2022granted Jun 2022Apr 2022North Lincolnshire6.1
Frederick Gough School, Grange Lane Southrooftop solarrooftop solar0.2approved, not builtupdated Jan 2023Oct 2022granted Nov 2022Jan 2023North Lincolnshire6.1
Chapel Lane Energy storage facilitybattery storagebattery storage—approved, not builtupdated Dec 2025Jan 2023granted Jan 2024Dec 2025North Lincolnshire6.3

Distance from the average position of the DN15 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm123421314
Rooftop solar13211006.6
Wind farm400310
Wind turbine210010
Battery storage51400215

MW in pipeline: pending, approved and under-construction capacity.

How North Lincolnshire decides solar, wind and battery applications

ApplicationsNorth LincolnshireUK
Decided applications (solar, wind, battery)4710,236
Refused15 (32%)19%
Solar refused7 of 3312%
Onshore wind refused8 of 1045%
Battery storage refused0 of 416%
Median time from submission to decision10.0 weeks17.0 weeks
Appeals lodged / allowed6 / 4—

All projects in North Lincolnshire

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near DN15, 2 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.