Ironstone Quarry Wind Farm (7.5 MW)

Ironstone Quarry Wind Farm is a 7.5 MW wind farm project in North Lincolnshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 5 June 2013; the record was last updated on 31 December 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7.5 MWwind farm
refusedstatus in REPD
31 December 2014record last updated
North Lincolnshirecouncil area

Planning timeline

DateStage
17 May 2011Application submitted
5 June 2013Refused by the planning authority
21 November 2013Appeal lodged
23 December 2014Appeal refused
23 December 2014Secretary of State refused

Project details

Technology
wind farm
Capacity
7.5 MW
Status (REPD)
refused
Record last updated
31 December 2014
Operator or applicant
Waste Recycling Group
Planning authority
North Lincolnshire
Planning application reference
WF/2011/0528
Appeal reference
APP/Y2003/A/13/2207858
Turbines
3
Address (REPD)
Winterton Landfill Site Off Coleby Road, West Halton & Top Road, Winterton, Scunthorpe, Humberside
Council area (by location)
North Lincolnshire
Time to decision
107 weeks
REPD reference
4535

Who decides

ApplicationsNorth LincolnshireUK
Decided applications (solar, wind, battery)4710,236
Refused15 (32%)19%
Solar refused7 of 3312%
Onshore wind refused8 of 1045%
Battery storage refused0 of 416%
Median time from submission to decision10.0 weeks17.0 weeks
Appeals lodged / allowed6 / 4—

Other large projects within 10 km

ProjectTypeMWStatuskm
Winterton Landfill Site - Ground Mounted Solar PV Arrayssolar farm5under construction1.3
Winterton Road, Roxby Solar Farmsolar farm50application submitted2.9
Carr Lane Solar Farmsolar farm9approved, not built3.8
Bagmoorwind farm16operational5.1
Grangewind farm12.3operational5.9
Flixborough Industrial Estatesolar farm5operational6.9
North Wharf Solar Farmsolar farm6refused on appeal6.9
North Lincolnshire Green Energy Parkbattery storage30approved, not built7.2
Winterton Roadbattery storage95approved, not built7.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.6654, -0.6234).