Keadby Wind Farm (68 MW)
Keadby Wind Farm is a 68 MW wind farm project in North Lincolnshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 26 February 2015; the record was last updated on 27 February 2015.
68 MWwind farm
operationalstatus in REPD
27 February 2015record last updated
North Lincolnshirecouncil area
Planning timeline
| Date | Stage |
|---|---|
| 24 October 2003 | Application submitted |
| 28 February 2008 | Planning permission granted |
| 1 March 2013 | Construction started |
| 26 February 2015 | Operational |
Project details
- Technology
- wind farm
- Capacity
- 68 MW
- Status (REPD)
- operational
- Record last updated
- 27 February 2015
- Operator or applicant
- Scottish and Southern Energy (SSE)
- Planning authority
- North Lincolnshire
- Planning application reference
- 2003/1630
- Turbines
- 34
- Address (REPD)
- Near Teadby Near Scunthorpe Lincolnshire
- Council area (by location)
- North Lincolnshire
- Time to decision
- 227 weeks
- REPD reference
- 4260
Who decides
| Applications | North Lincolnshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 47 | 10,236 |
| Refused | 15 (32%) | 19% |
| Solar refused | 7 of 33 | 12% |
| Onshore wind refused | 8 of 10 | 45% |
| Battery storage refused | 0 of 4 | 16% |
| Median time from submission to decision | 10.0 weeks | 17.0 weeks |
| Appeals lodged / allowed | 6 / 4 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| North Moor Farm, Keadby | solar farm | 49.9 | application submitted | 1.6 |
| Solar Farm at Ealand Road | solar farm | 49.9 | application submitted | 2.3 |
| North Lincolnshire Green Energy Park | battery storage | 30 | approved, not built | 4.2 |
| North Wharf Solar Farm | solar farm | 6 | refused on appeal | 4.6 |
| Flixborough Industrial Estate | solar farm | 5 | operational | 4.6 |
| Grange | wind farm | 12.3 | operational | 5.1 |
| Bagmoor | wind farm | 16 | operational | 6.6 |
| Old River Don Wind Farm | wind farm | 18 | refused | 7.0 |
| Winterton Road | battery storage | 95 | approved, not built | 8.2 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.6118, -0.7637).