Energy Projects Near You

Old River Don Wind Farm (18 MW)

Old River Don Wind Farm is an 18 MW wind farm project in North Lincolnshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 23 September 2015; the record was last updated on 6 October 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

18 MWwind farm
refusedstatus in REPD
6 October 2015record last updated
North Lincolnshirecouncil area

Planning timeline

DateStage
30 June 2014Application submitted
23 September 2015Refused by the planning authority

Project details

Technology
wind farm
Capacity
18 MW
Status (REPD)
refused
Record last updated
6 October 2015
Operator or applicant
REG Windpower
Planning authority
North Lincolnshire
Planning application reference
WF/2014/0710
Turbines
6
Address (REPD)
Land off, Godnow Road, Crowle
Council area (by location)
North Lincolnshire
Time to decision
64 weeks
REPD reference
4405

Who decides

ApplicationsNorth LincolnshireUK
Decided applications (solar, wind, battery)4710,236
Refused15 (32%)19%
Solar refused7 of 3312%
Onshore wind refused8 of 1045%
Battery storage refused0 of 416%
Median time from submission to decision10.0 weeks17.0 weeks
Appeals lodged / allowed6 / 4—

Other large projects within 10 km

ProjectTypeMWStatuskm
Twin Riverswind farm28.7operational2.3
Tween Bridge Windfarmwind farm44operational4.6
The Tween Bridge Solar Farmsolar farm800application submitted4.6
Thorne Farmsolar farm5operational5.1
Solar Farm at Ealand Roadsolar farm49.9application submitted6.3
Goole Fieldswind farm32.8operational6.3
Keadby Wind Farmwind farm68operational7.0
Charity Farmwind farm32application withdrawn7.4
Goole Fields ll Wind Farmwind farm34.9operational7.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.6102, -0.8696).