Goole Fields (32.8 MW wind farm)

Goole Fields is a 32.8 MW wind farm project in East Riding of Yorkshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 11 August 2014; the record was last updated on 18 August 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

32.8 MWwind farm
operationalstatus in REPD
18 August 2014record last updated
East Riding of Yorkshirecouncil area

Planning timeline

DateStage
1 April 2003Application submitted
1 September 2003Planning permission granted
1 March 2012Construction started
11 August 2014Operational

Project details

Technology
wind farm
Capacity
32.8 MW
Status (REPD)
operational
Record last updated
18 August 2014
Operator or applicant
RWE npower
Planning authority
East Riding of Yorkshire
Planning application reference
03/01987
Turbines
16
Address (REPD)
Goole Fields Parish , East Riding of Yorkshire
Council area (by location)
East Riding of Yorkshire
Time to decision
22 weeks
REPD reference
4373

Who decides

ApplicationsEast Riding of YorkshireUK
Decided applications (solar, wind, battery)14310,236
Refused26 (18%)19%
Solar refused1 of 5912%
Onshore wind refused24 of 6345%
Battery storage refused1 of 2116%
Median time from submission to decision18.9 weeks17.0 weeks
Appeals lodged / allowed4 / 10—

Other large projects within 10 km

ProjectTypeMWStatuskm
Goole Fields ll Wind Farmwind farm34.9operational1.2
Charity Farmwind farm32application withdrawn2.3
Rawcliffe Bridge Wind Farmwind farm10refused2.8
Thorne Farmsolar farm5operational4.4
Rawcliffe Estate, Bridge Lane Solar Farmsolar farm6approved, not built4.5
Tween Bridge Windfarmwind farm44operational5.7
The Tween Bridge Solar Farmsolar farm800application submitted5.9
Old River Don Wind Farmwind farm18refused6.3
Twin Riverswind farm28.7operational6.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.6659, -0.8893).