Tween Bridge Windfarm (44 MW)

Tween Bridge Windfarm is a 44 MW wind farm project in Doncaster, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 27 February 2012; the record was last updated on 23 August 2012.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

44 MWwind farm
operationalstatus in REPD
23 August 2012record last updated
Doncastercouncil area

Planning timeline

DateStage
23 January 2004Application submitted
28 February 2008Planning permission granted
1 May 2011Construction started
27 February 2012Operational

Project details

Technology
wind farm
Capacity
44 MW
Status (REPD)
operational
Record last updated
23 August 2012
Operator or applicant
E.ON Renewables
Planning authority
Doncaster
Planning application reference
04/0314/P/CIR2
Turbines
22
Address (REPD)
Tween Bridge, Thorne, Doncaster, South Yorks
Council area (by location)
Doncaster
Time to decision
214 weeks
REPD reference
3928

Who decides

ApplicationsDoncasterUK
Decided applications (solar, wind, battery)4310,236
Refused3 (7%)19%
Solar refused1 of 2712%
Onshore wind refused1 of 545%
Battery storage refused1 of 1116%
Median time from submission to decision17.0 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
The Tween Bridge Solar Farmsolar farm800application submitted0.2
Thorne Farmsolar farm5operational1.5
Twin Riverswind farm28.7operational2.6
Old River Don Wind Farmwind farm18refused4.6
Goole Fieldswind farm32.8operational5.7
Rawcliffe Bridge Wind Farmwind farm10refused6.3
Goole Fields ll Wind Farmwind farm34.9operational6.9
Rawcliffe Estate, Bridge Lane Solar Farmsolar farm6approved, not built6.9
Charity Farmwind farm32application withdrawn7.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.6223, -0.9356).