Energy Projects Near You

Solar, wind and battery projects near Doncaster (DN8)

28 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of DN8 (Doncaster): 2 are waiting for a planning decision, 12 approved but not yet running, 9 operational. The largest live scheme is Thorpe Marsh Power Station (1,450 MW battery storage, approved on 28 January 2025, not yet built), 9.4 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

28projects within 10 km
2awaiting a decision
12approved, not running
9operational

Projects within 10 km of DN8

Projects of 1 MW and more (20)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
The Tween Bridge Solar Farmsolar farmsolar farm800application submittedupdated Oct 2025Aug 2025—Oct 2025Doncaster1.4
The Tween Bridge Solar Farmbattery storagebattery storage400application submittedupdated Oct 2025Aug 2025—Oct 2025Doncaster1.4
Tween Bridge Windfarmwind farmwind farm44operationalupdated Aug 2012Jan 2004granted Feb 2008Aug 2012Doncaster1.5
Thorne Farmsolar farmsolar farm5operationalupdated Dec 2015Sep 2014granted Apr 2015Dec 2015Doncaster2.7
Twin Riverswind farmwind farm28.7operationalupdated Apr 2017Jan 2004granted Jan 2009Apr 2017Doncaster3.4
Old River Don Wind Farmwind farmwind farm18refusedupdated Oct 2015Jun 2014refused Sep 2015Oct 2015North Lincolnshire5.7
Goole Fieldswind farmwind farm32.8operationalupdated Aug 2014Apr 2003granted Sep 2003Aug 2014East Riding of Yorkshire7.1
Rawcliffe Bridge Wind Farmwind farmwind farm10refusedupdated Apr 2015Feb 2014refused Feb 2015Apr 2015East Riding of Yorkshire7.3
Warren Farm Solar Farm & Battery Storagesolar farmsolar farm49.9approved, not built may be out of dateupdated Feb 2022Aug 2021granted Mar 2022Feb 2022Doncaster7.6
Rawcliffe Estate, Bridge Lane Solar Farmsolar farmsolar farm6approved, not builtupdated Jan 2025Aug 2024granted Dec 2024Jan 2025East Riding of Yorkshire7.7
Goole Fields ll Wind Farmwind farmwind farm34.9operationalupdated Mar 2017Jan 2012granted May 2014Mar 2017East Riding of Yorkshire8.2
Croda Chemicals Europewind turbinewind turbine3operationalupdated Dec 2009Apr 2006granted Oct 2006Dec 2009East Riding of Yorkshire8.2
Aire & Calder Wind Farmwind farmwind farm45application withdrawnupdated Jun 2011Aug 2005—Jun 2011East Riding of Yorkshire8.3
Charity Farmwind farmwind farm32application withdrawnupdated Mar 2011Aug 2009—Mar 2011East Riding of Yorkshire9.3
Thorpe Marsh Power Stationbattery storagebattery storage1,450approved, not builtupdated Nov 2025Apr 2023granted Jan 2025Nov 2025Doncaster9.4
Thorpe Marsh Power Station, Marsh Lanebattery storagebattery storage1,400approved, not builtupdated Feb 2025Apr 2023granted Jan 2025Feb 2025Doncaster9.4
Fenwick Solar Farm & Battery Storagesolar farmsolar farm238approved, not builtupdated Mar 2026Nov 2024granted Feb 2026Mar 2026Doncaster9.7
Ikea Distribution Centrerooftop solarrooftop solar1.7operationalupdated Jul 2016Feb 2014granted Apr 2014Jul 2016Doncaster9.7
Land at Pollington Airfieldsolar farmsolar farm5operationalupdated Feb 2016May 2015granted Jul 2015Feb 2016East Riding of Yorkshire9.8
Green Lane (Westgate)solarsolar2refusedupdated Aug 2014Nov 2013refused Jul 2014Aug 2014North Lincolnshire9.9
Smaller schemes under 1 MW, mostly rooftop solar (8)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Tudworth Field Road, Hatfieldrooftop solarrooftop solar0.3operationalupdated Apr 2022Mar 2022granted Apr 2022Apr 2022Doncaster3.2
Tudworth Field Road, Hatfieldrooftop solarrooftop solar0.2under constructionupdated Apr 2022Mar 2022granted Jul 2022Apr 2022Doncaster3.2
Greenland Hall Farm – Ground Mounted Solar Panelssolar farmsolar farm—approved, not built may be out of dateupdated Jul 2023May 2023granted Jul 2023Jul 2023East Riding of Yorkshire5.5
Commons Farm, Thorne Roadsolar farmsolar farm0.4approved, not built may be out of dateupdated Aug 2023Jun 2023granted Jul 2023Aug 2023East Riding of Yorkshire6.7
Warren Farm Solar Farm & Battery Storagebattery storagebattery storage—approved, not built may be out of dateupdated Feb 2022Aug 2021granted Mar 2022Feb 2022Doncaster7.6
Fenwick Solar Farm & Battery Storagebattery storagebattery storage—approved, not builtupdated Mar 2026Nov 2024granted Feb 2026Mar 2026Doncaster9.7
Tesco Distribution Centre. Tom Pudding Wayrooftop solarrooftop solar0.6approved, not builtupdated Nov 2025Jun 2025granted Jul 2025Nov 2025East Riding of Yorkshire9.7
Jj Foodservice Limited, Derbyshire Courtrooftop solarrooftop solar0.2approved, not builtupdated Sep 2023Jul 2023granted Aug 2023Sep 2023Doncaster9.7

Distance from the average position of the DN8 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm815201,094
Rooftop solar503201
Solar100010
Wind farm800420
Wind turbine100100
Battery storage514003,250

MW in pipeline: pending, approved and under-construction capacity.

How Doncaster decides solar, wind and battery applications

ApplicationsDoncasterUK
Decided applications (solar, wind, battery)4310,236
Refused3 (7%)19%
Solar refused1 of 2712%
Onshore wind refused1 of 545%
Battery storage refused1 of 1116%
Median time from submission to decision17.0 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

All projects in Doncaster

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near DN8, 4 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.