Goole Fields ll Wind Farm (34.9 MW)

Goole Fields ll Wind Farm is a 34.9 MW wind farm project in East Riding of Yorkshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 14 November 2016; the record was last updated on 31 March 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

34.9 MWwind farm
operationalstatus in REPD
31 March 2017record last updated
East Riding of Yorkshirecouncil area

Planning timeline

DateStage
6 January 2012Application submitted
22 May 2014Planning permission granted
14 August 2015Construction started
14 November 2016Operational

Project details

Technology
wind farm
Capacity
34.9 MW
Status (REPD)
operational
Record last updated
31 March 2017
Operator or applicant
RWE Npower Renewables
Planning authority
East Riding of Yorkshire
Planning application reference
11/05923/STPLFE
Turbines
17
Address (REPD)
approximately 2km south of Old Goole, immediately to the west of the consented Goole Fields Wind Farm.
Council area (by location)
East Riding of Yorkshire
Time to decision
124 weeks
REPD reference
4070

Who decides

ApplicationsEast Riding of YorkshireUK
Decided applications (solar, wind, battery)14310,236
Refused26 (18%)19%
Solar refused1 of 5912%
Onshore wind refused24 of 6345%
Battery storage refused1 of 2116%
Median time from submission to decision18.9 weeks17.0 weeks
Appeals lodged / allowed4 / 10—

Other large projects within 10 km

ProjectTypeMWStatuskm
Goole Fieldswind farm32.8operational1.2
Charity Farmwind farm32application withdrawn1.8
Rawcliffe Bridge Wind Farmwind farm10refused2.5
Rawcliffe Estate, Bridge Lane Solar Farmsolar farm6approved, not built4.3
Thorne Farmsolar farm5operational5.5
Tween Bridge Windfarmwind farm44operational6.9
Rusholme Grangebattery storage40operational6.9
The Tween Bridge Solar Farmsolar farm800application submitted7.0
Rusholme Wind Farmwind farm24operational7.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.6768, -0.8868).