Energy Projects Near You

Solar, wind and battery projects near Doncaster (DN6)

32 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of DN6 (Doncaster): 5 are waiting for a planning decision, 19 approved but not yet running, 4 operational. The largest live scheme is Thorpe Marsh Power Station (1,450 MW battery storage, approved on 28 January 2025, not yet built), 6.5 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

32projects within 10 km
5awaiting a decision
19approved, not running
4operational

Projects within 10 km of DN6

Projects of 1 MW and more (22)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Croft Farm, Askern Road Solar Array & Hydrogen Plantsolar farmsolar farm2.5under constructionupdated Mar 2026Sep 2022granted May 2023Mar 2026Doncaster1.9
Askern Colliery solar farmsolar farmsolar farm5operationalupdated Nov 2015Aug 2014granted Dec 2014Nov 2015Doncaster2.8
Norton Community Wind Turbineswind farmwind farm5refusedupdated Mar 2017Aug 2012refused Mar 2017Mar 2017Doncaster3.5
Woodlandsbattery storagebattery storage1.2approved, not built may be out of dateupdated Jul 2022Mar 2022granted Jul 2022Jul 2022Doncaster4.2
Long Lands Lanebattery storagebattery storage12abandonedupdated Feb 2019Oct 2017—Feb 2019Doncaster4.2
The Balk, Almholmebattery storagebattery storage1,025approved, not builtupdated Oct 2024Nov 2023granted Oct 2024Oct 2024Doncaster4.6
The Balk, Almholme Solar Farmsolar farmsolar farm49.9approved, not builtupdated Oct 2024Nov 2023granted Oct 2024Oct 2024Doncaster4.6
Hampole Wind Farmwind farmwind farm8operationalupdated Oct 2018Sep 2008granted Dec 2009Oct 2018Doncaster5.6
Fordtead Lane, Thorpe Marsh Battery Energy Facilitybattery storagebattery storage180approved, not builtupdated May 2024Sep 2023granted Apr 2024May 2024Doncaster5.7
Moorhouse Grange, Moorhouse Lane Solar Farmsolar farmsolar farm30application submittedupdated Sep 2025Aug 2025—Sep 2025Doncaster5.7
Elmsall Way Warehouserooftop solarrooftop solar2.4operationalupdated Sep 2022Dec 2019granted May 2020Sep 2022Wakefield6.1
Fenwick Solar Farm & Battery Storagesolar farmsolar farm238approved, not builtupdated Mar 2026Nov 2024granted Feb 2026Mar 2026Doncaster6.3
Elmsall Way, South Elmsallrooftop solarrooftop solar3under constructionupdated May 2022May 2022granted Sep 2022May 2022Wakefield6.4
Finlay Beverages, Elmsall Wayrooftop solarrooftop solar1.6approved, not builtupdated Aug 2024May 2024granted Aug 2024Aug 2024Wakefield6.4
Thorpe Marsh Power Stationbattery storagebattery storage1,450approved, not builtupdated Nov 2025Apr 2023granted Jan 2025Nov 2025Doncaster6.5
Thorpe Marsh Power Station, Marsh Lanebattery storagebattery storage1,400approved, not builtupdated Feb 2025Apr 2023granted Jan 2025Feb 2025Doncaster6.5
Butt Lane, Hooton Pagnell Solar Farmsolar farmsolar farm49.9application submittedupdated Jan 2026Dec 2025—Jan 2026Doncaster6.8
Butt Lane, Hooton Pagnell Battery Energy Storagebattery storagebattery storage30application submittedupdated Jan 2026Dec 2025—Jan 2026Doncaster6.8
Marr Hall Farm, Barnsley Road Solar Farmsolar farmsolar farm40refusedupdated Jan 2026Jan 2024refused Dec 2025Jan 2026Doncaster6.9
Cutts Bros, Wharf Roadbattery storagebattery storage50approved, not builtupdated Nov 2024May 2024granted Oct 2024Nov 2024Doncaster8.0
Marr Windfarmwind farmwind farm8operationalupdated Mar 2012Dec 2006granted Jul 2007Mar 2012Doncaster8.3
South Kirkby Business Parkbattery storagebattery storage10permission expiredupdated Jan 2020Oct 2017granted Jan 2018Jan 2020Wakefield10.0
Smaller schemes under 1 MW, mostly rooftop solar (10)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Moorhouse Grange, Moorhouse Lane Battery Energybattery storagebattery storage—application submittedupdated Sep 2025Aug 2025—Sep 2025Doncaster5.7
Don Valley Academy, Jossey Lanerooftop solarrooftop solar0.3approved, not builtupdated Jan 2026Oct 2025granted Dec 2025Jan 2026Doncaster5.8
Fenwick Solar Farm & Battery Storagebattery storagebattery storage—approved, not builtupdated Mar 2026Nov 2024granted Feb 2026Mar 2026Doncaster6.3
Upton Primary School, Waggon Lanerooftop solarrooftop solar0.2application submittedupdated Nov 2025Oct 2025—Nov 2025Wakefield6.7
Aggreko UK, Sandall Stones Roadrooftop solarrooftop solar0.2approved, not builtupdated Aug 2025May 2025granted Jul 2025Aug 2025Doncaster7.8
Aggreko UK, Sandall Stones Roadbattery storagebattery storage—approved, not builtupdated Aug 2025May 2025granted Jul 2025Aug 2025Doncaster7.8
Premier Logistics Park, Churchill Roadrooftop solarrooftop solar—approved, not builtupdated Mar 2026Dec 2025granted Feb 2026Mar 2026Doncaster8.0
Langthwaite Road, South Kirkbysolar farmsolar farm0.5approved, not built may be out of dateupdated Jan 2022Dec 2021granted Mar 2022Jan 2022Wakefield8.8
Sainsburys, Thorne Roadrooftop solarrooftop solar0.6approved, not builtupdated Jun 2026Apr 2026granted May 2026Jun 2026Doncaster8.9
Data Drive, South Kirkbyrooftop solarrooftop solar0.2approved, not builtupdated Sep 2023Jul 2023granted Sep 2023Sep 2023Wakefield9.8

Distance from the average position of the DN6 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm82411370
Rooftop solar917106.1
Wind farm300210
Battery storage1228004,136

MW in pipeline: pending, approved and under-construction capacity.

How Doncaster decides solar, wind and battery applications

ApplicationsDoncasterUK
Decided applications (solar, wind, battery)4310,236
Refused3 (7%)19%
Solar refused1 of 2712%
Onshore wind refused1 of 545%
Battery storage refused1 of 1116%
Median time from submission to decision17.0 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

All projects in Doncaster

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near DN6, 2 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.