Cutts Bros, Wharf Road (50 MW battery storage)

Cutts Bros, Wharf Road is a 50 MW battery storage project in Doncaster, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 29 October 2024, not yet built; the record was last updated on 12 November 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

50 MWbattery storage
approved, not builtstatus in REPD
12 November 2024record last updated
Doncastercouncil area

Planning timeline

DateStage
28 May 2024Application submitted
29 October 2024Planning permission granted
29 October 2029Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
50 MW
Status (REPD)
approved, not built
Record last updated
12 November 2024
Operator or applicant
Newton Energi Limited
Planning authority
Doncaster
Planning application reference
24/00841/FUL
Address (REPD)
Cutts Bros, Wharf Road, Doncaster
Council area (by location)
Doncaster
Time to decision
22 weeks
Name in REPD
Cutts Bros, Wharf Road - Battery Storage Facility
REPD reference
16514

Earlier applications for this site

ApplicationMWSubmittedOutcome
Cutts Bros, Wharf Road 23/01843/FUL5025 October 2023refused 12 December 2023

Who decides

ApplicationsDoncasterUK
Decided applications (solar, wind, battery)4310,236
Refused3 (7%)19%
Solar refused1 of 2712%
Onshore wind refused1 of 545%
Battery storage refused1 of 1116%
Median time from submission to decision17.0 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
J3 Business Parkbattery storage16approved, not built3.2
J3 Business Parkbattery storage10under construction3.2
The Balk, Almholme Solar Farmsolar farm49.9approved, not built3.9
The Balk, Almholmebattery storage1,025approved, not built3.9
Fordtead Lane, Thorpe Marsh Battery Energy Facilitybattery storage180approved, not built4.1
Fenwick Solar Farm & Battery Storagesolar farm238approved, not built5.9
Thorpe Marsh Power Station, Marsh Lanebattery storage1,400approved, not built6.1
Thorpe Marsh Power Stationbattery storage1,450approved, not built6.1
Marr Hall Farm, Barnsley Road Solar Farmsolar farm40refused6.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.5321, -1.1292).