Fordtead Lane, Thorpe Marsh Battery Energy Facility (180 MW)

Fordtead Lane, Thorpe Marsh Battery Energy Facility is a 180 MW battery storage project in Doncaster, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 30 April 2024, not yet built; the record was last updated on 13 May 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

180 MWbattery storage
approved, not builtstatus in REPD
13 May 2024record last updated
Doncastercouncil area

Planning timeline

DateStage
13 September 2023Application submitted
30 April 2024Planning permission granted
30 April 2029Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
180 MW
Status (REPD)
approved, not built
Record last updated
13 May 2024
Operator or applicant
Newton Energi Limited
Planning authority
Doncaster
Planning application reference
23/01746/FULM
Address (REPD)
Land At Fordstead Lane Almholme Doncaster
Council area (by location)
Doncaster
Time to decision
33 weeks
Name in REPD
Fordtead Lane, Thorpe Marsh - Battery Energy Facility
REPD reference
14932

Who decides

ApplicationsDoncasterUK
Decided applications (solar, wind, battery)4310,236
Refused3 (7%)19%
Solar refused1 of 2712%
Onshore wind refused1 of 545%
Battery storage refused1 of 1116%
Median time from submission to decision17.0 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
The Balk, Almholme Solar Farmsolar farm49.9approved, not built1.4
The Balk, Almholmebattery storage1,025approved, not built1.4
Fenwick Solar Farm & Battery Storagesolar farm238approved, not built2.0
Thorpe Marsh Power Stationbattery storage1,450approved, not built2.2
Thorpe Marsh Power Station, Marsh Lanebattery storage1,400approved, not built2.2
Cutts Bros, Wharf Roadbattery storage50approved, not built4.1
Warren Farm Solar Farm & Battery Storagesolar farm49.9approved, not built5.4
Long Lands Lanebattery storage12abandoned6.6
Askern Colliery solar farmsolar farm5operational6.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.5668, -1.1097).